Bombay High Court
Property and Real Estate LawCivil Procedure and Evidence

RERA delay interest runs until possession is handed over unless the allottee unjustifiably refuses a valid offer.

Orbit Enterprises vs Vazirani Realty Private Limited

Bombay High CourtJUDGMENT: October 14, 20262 MIN READSOURCE JUDGMENT
RERA delay interest runs until possession is handed over unless the allottee unjustifiably refuses a valid offer.. Orbit Enterprises vs Vazirani Realty Private Limited. Bombay High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

Orbit Enterprises, the promoter, agreed to deliver nine units to Vazirani Realty by 31 May 2015 or 30 June 2017, depending on the units.

Source reference: p. 2–6

The promoter obtained the Occupation Certificate on 12 February 2021, but the units were delivered only on 24 September 2021, following an order in the allottee’s writ petition.

Source reference: p. 2–6

The MahaRERA Authority awarded delayed-possession interest only until the date of the Occupation Certificate and allowed a COVID-19 moratorium.

Source reference: p. 2–6

On the allottee’s appeals, the Appellate Tribunal directed interest from the agreed possession dates until actual delivery and disallowed the moratorium.

Source reference: p. 2–6

The promoter challenged that decision in these second appeals.

Source reference: p. 2–6
02

Issues

1. Whether the promoter’s communication dated 25 February 2021 established an offer of possession sufficient to limit its liability to pay interest before actual delivery of the units

Source reference: p. 7–9, 13–15

2. Whether the Appellate Tribunal could disallow the COVID-19 moratorium when the allottee had not separately challenged that benefit

Source reference: p. 7–8, 16–18
03

Law Applied

Section 18(1) of the Real Estate (Regulation and Development) Act, 2016 (RERA) entitles an allottee who continues with the project to interest for each month of delay until possession is handed over;

Source reference: p. 11–12

Sections 18(1) and 19(4) also provide an allottee who withdraws from the project with a right to refund and interest.

Source reference: p. 11–12

Section 19(10) requires the allottee to take physical possession within two months of the Occupation Certificate.

Source reference: p. 11–12

Under Order XLI Rule 33 of the Code of Civil Procedure, 1908, an appellate court may make an order necessary to do complete justice, subject to the limits identified in Banarsi v. Ram Phal and K. Muthuswami Gounder v. N. Palaniappa Gounder.

Source reference: p. 16–18

Newtech Promoters and Developers Pvt. Ltd. v. State of Uttar Pradesh and Imperia Structures Ltd. v. Anil Patni were cited for the allottee’s statutory rights under RERA.

Source reference: p. 12

Under State of Maharashtra v. Ramdas Shrinivas Nayak, a party disputing a court’s record of what occurred must seek correction from that court; the recorded account cannot be contradicted later by evidence or submissions.

Source reference: p. 14–15
04

Reasoning

The Tribunal found that the promoter had not established that it offered possession, and the High Court declined to revisit that recorded finding in the second appeals.

Source reference: p. 13–15

The 25 February 2021 letter did not alter the result: it concerned only five units, sought further payment and execution of agreements already made, and did not establish an offer of possession for all units.

Source reference: p. 13–15

The allottee’s writ petition seeking delivery also contradicted the promoter’s account.

Source reference: p. 13–15

Accordingly, interest continued until actual delivery.

Source reference: p. 13–15

The agreed possession dates preceded the COVID-19 restrictions by years, so the moratorium did not apply.

Source reference: p. 16–18

Further, because the allottee’s appeals sought interest through the date of actual possession, the challenge to the moratorium was implicit; the Tribunal could address it under Order XLI Rule 33.

Source reference: p. 16–18
05

Holding

The High Court held that no substantial question of law arose for consideration.

It dismissed all three second appeals with costs and disposed of the interim applications.

Source reference: p. 19
06

Acts & Sections Cited

3 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Real Estate (Regulation and Development) Act, 2016.2

Code of Civil Procedure, 19081

Bombay High Court

Original Court PDF

Orbit EnterprisesvsVazirani Realty Private Limited

Bombay High Court · October 14, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment