Uttarakhand High Court

Rule 4.2.3 of Procurement Rules applies to high-value lump sum contracts involving design and execution.

MS PATNI ENGINEERING AND CONSTRUCTION vs STATE OF UTTARAKHAND

Uttarakhand High CourtJUDGMENT: May 14, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Public Works Department (PWD), Nainital, issued a tender notice dated 30.04.2026 for hillside cutting, muck disposal, and construction work on National Highway No. 87

Source reference: para. 2

The Petitioner challenged Clause 11.1(A)(ix) of the Instructions to Bidders (ITB), which mandated that bidders visit the site with a departmental engineer and obtain a certificate from the Executive Engineer to be considered responsive

Source reference: para. 3-4

Additionally, the Petitioner challenged the non-disclosure of individual item rates in the Bill of Quantities (BOQ), alleging a violation of Rule 4.7.3 of the Procurement Rules, 2025

Source reference: para. 5

During the proceedings, the State informed the Court that the controversial site-visit clause had been deleted via a corrigendum dated 04.05.2026

Source reference: para. 7
02

Issues

1. Whether Clause 11.1 Sub-Clause (A)(ix) of the ITB, requiring a site-visit certificate, was arbitrary and liable to be quashed

Source reference: para. 4

2. Whether the respondents were required to specify rates of individual items in the BOQ under Rule 4.7.3, or if the disclosure of a lump sum amount was permissible under Rule 4.2.3 of the Uttarakhand Procurement Rules, 2025

Source reference: para. 5, 9
03

Law Applied

Rule 4.2.2 applies to "Item Contracts" for work of an emergent nature or specific lower-value thresholds (up to Rs. 10 lacs), requiring detailed item rates

Source reference: para. 9, 11

Conversely, Rule 4.2.3 governs high-value contracts (exceeding Rs. 10 lacs) involving design, procurement, and execution, allowing for "Lump Sum" estimated amounts

Source reference: para. 9-11
04

Reasoning

Regarding the first issue, the Court noted that the State had already deleted the restrictive site-visit clause via corrigendum, rendering the Petitioner's grievance on that point moot

Source reference: para. 7-8

On the second issue, the Court rejected the Petitioner’s reliance on Rule 4.7.3/4.2.2. It accepted the State’s contention that because the contract value was Rs. 546.83 lacs—significantly exceeding the Rs. 10 lac threshold—and involved complex works like hillside cutting and drainage design, it fell squarely under Rule 4.2.3

Source reference: para. 10-12

The Court reasoned that the detailed tendering process for high-value lump sum contracts does not necessitate the disclosure of individual item rates as required in emergent item-rate contracts under Rule 4.2.2

Source reference: para. 11
05

Holding

The Court held that the petition lacked merit as the first grievance was voluntarily rectified by the State and the second grievance failed to account for the correct statutory classification of the contract

The Writ Petition was dismissed, and the interim order was vacated

Source reference: para. 14-15
Uttarakhand High Court

Original Court PDF

MS PATNI ENGINEERING AND CONSTRUCTIONvsSTATE OF UTTARAKHAND

Uttarakhand High Court · May 14, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment