Facts
The petitioner owned lands in Survey Nos.15/2E and 15/4 at Achangulam Village, Kayathar Taluk, Thoothukudi District, which it had acquired for agro-farming and on which it had installed solar panels.
Source reference: para. 5The first respondent issued Notice No.200 dated 11 August 2026, proposing to utilise the lands for stringing cables and erecting transmission towers to evacuate power from the Kudankulam Power Plant.
Source reference: para. 3The petitioner challenged the notice under Article 226 of the Constitution, principally contending that it had been issued without prior notice and was inconsistent with the permission granted under G.O.Ms.No.419.
Source reference: para. 4The first respondent contended that statutory publications had already been made on 12 August 2024 and 22 January 2025, with the approval of the Government of India, followed by a Gazette notification dated 6 April 2026.
Source reference: para. 6Issues
Whether the impugned notice issued for laying transmission cables and erecting towers under the Indian Telegraph Act, 1885, read with the Electricity Act, 2003, was liable to be quashed for want of prior notice to the petitioner.
Source reference: paras. 3–4, 10–11Whether the petitioner’s land-reform permission under G.O.Ms.No.419, dated 14 March 2026, prevented the respondents from using the land for the proposed transmission line.
Source reference: para. 5Whether the petitioner’s remedy, if aggrieved by the use of the land or the compensation, was confined to determination and challenge of compensation under Sections 10(d) and 16(3) of the Indian Telegraph Act, 1885.
Source reference: paras. 8–12Law Applied
The Court applied Section 10 of the Indian Telegraph Act, 1885, particularly Section 10(d), which authorises the exercise of telegraph-line powers over property while requiring payment of compensation for damage sustained by the owner or occupier.
Source reference: paras. 8–12Section 16(3) of the Indian Telegraph Act provides a remedy before the District Court against the compensation determined by the competent authority.
Source reference: paras. 8–12These provisions were treated as applicable to the implementation of transmission projects under the Electricity Act, 2003.
Source reference: paras. 8–12The Court also considered G.O.(Ms.) No.63, Energy (A1) Department, dated 22 November 2017, prescribing the method for determining compensation, and G.O.(Ms.) No.86, Energy (A1) Department, dated 30 October 2019, enhancing the prescribed amount.
Source reference: para. 7The Court held that the powers under Section 10(d) are wide and that prior notice is required only in cases involving land belonging to local authorities, according to the respondents’ submission accepted in the Court’s reasoning.
Source reference: paras. 8, 11Reasoning
The Court held that the first respondent’s proposal to lay cables and erect transmission towers was made under the statutory powers conferred by the Indian Telegraph Act, read with the Electricity Act, and followed prior governmental approval and statutory publications.
Source reference: paras. 6, 10–11The petitioner’s reliance on the later permission under G.O.Ms.No.419 did not invalidate the transmission project, particularly as the project-related publications had preceded that Government Order.
Source reference: para. 6The Court further concluded that the absence of prior individual notice did not vitiate the impugned notice because the statutory scheme did not require such notice in respect of private land in the circumstances presented.
Source reference: paras. 8, 10–11Any injury caused by laying the cables or towers was compensable under Section 10(d), with compensation to be assessed in accordance with the applicable Government Orders.
Source reference: para. 12The petitioner’s statutory remedy, if dissatisfied with that determination, was an appeal under Section 16(3) before the District Court.
Source reference: para. 12Holding
The Court dismissed the writ petition, holding that the challenge to Notice No.200 dated 11 August 2026 was without merit.
It directed the second respondent, the District Collector, Thoothukudi District, to determine the compensation payable to the petitioner after the cables and transmission towers were laid and strung, in accordance with Section 10(d) of the Indian Telegraph Act and the applicable Government Orders.
Source reference: para. 13The connected miscellaneous petitions were closed, with no order as to costs.
Source reference: para. 14Acts & Sections Cited
2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Indian Telegraph Act, 18852
Original Court PDF
M/s. Bharathi Agro Bio FarmvsM/s. Kudankulam ISTS Transmi
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
