01Facts
The petitioner, a registered small enterprise under the MSMED Act, supplied conveyor structures to the respondent
¶ 2.1-2.2Alleging non-payment of dues amounting to Rs. 77,04,901, the petitioner approached the Micro and Small Enterprise Facilitation Council (MSEF Council) under Section 18(1) of the MSMED Act
¶ 2.4On April 22, 2025, the Council recorded that the respondent sought time to reply and ordered that if the respondent failed to file submissions, the case would be forwarded for arbitration
¶ 2.7However, the Council did not formally terminate conciliation or appoint an arbitrator
¶ 2.8The petitioner then filed the present petition under Section 11(6)(c) of the Arbitration and Conciliation Act, 1996, seeking the appointment of a sole arbitrator, despite the absence of an independent written arbitration agreement between the parties
¶ 1, 602Issues
i.Whether a petitioner can approach the High Court under Section 11(6) of the Arbitration Act for the appointment of an arbitrator while conciliation proceedings are still pending before the MSEF Council and no formal reference to arbitration has been made under Section 18(3) of the MSMED Act.
¶ 703Law Applied
The court primarily applied Section 18 of the MSMED Act, which provides a three-tier statutory mechanism: reference, conciliation, and arbitration
¶ 9Under Section 18(3), the provisions of the Arbitration Act apply only "then"—specifically after conciliation fails and stands terminated, and the Council either takes up the dispute or refers it to an institution
¶ 12, 20The court relied on Gujarat State Civil Supplies Corporation Ltd. v. Mahakali Foods Pvt. Ltd., which established that the MSMED Act, being a special statute, overrides the Arbitration Act once its mechanism is triggered
¶ 8, 13It further cited Jagdish Chander v. Ramesh Chander, holding that the existence of a written arbitration agreement under Section 7 of the Arbitration Act is a sine qua non for exercising jurisdiction under Section 11
¶ 30Shobhana Gupta v. Atlas Cycles Haryana Ltd., which clarified that the deeming fiction of an arbitration agreement under MSMED Section 18(3) does not arise until the arbitration stage is formally reached
¶ 25Provisions in the judgment · 35 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 24 provisions
Section 2Section 7Section 11Section 20Section 23Section 24Section 25Section 65Section 66Section 67Section 68Section 69Section 70Section 71Section 72Section 73Section 74Section 75Section 76Section 77Section 78Section 79Section 80Section 81Micro, Small and Medium Enterprises Development Act, 2006 11 provisions
Section 15Section 16Section 17Section 18Section 19Section 20Section 21Section 22Section 23Section 24Section 2504Reasoning
The Court observed that the petitioner voluntarily invoked the statutory jurisdiction of the MSEF Council under Section 18
¶ 18Under the scheme of Section 18(3), the Arbitration Act is only applicable at the post-referral stage, marked by the formal termination of conciliation
¶ 22, 24In this case, the MSEF Council was still seized of the matter as a conciliator, and no order of termination or referral had been passed; the Council's observation regarding "forwarding for arbitration" was merely conditional
¶ 32Consequently, the "statutory arbitration agreement" contemplated by the MSMED Act had not yet come into existence
¶ 33Furthermore, because there was no independent written arbitration agreement between the parties as required by Section 7 of the Arbitration Act, the court held that the prerequisite for invoking Section 11(6) was absent
¶ 26, 35The Court distinguished previous precedents by noting that in those cases, either a separate arbitration agreement existed or the Council had failed to initiate the statutory process entirely
¶ 36-3805Holding
The Court held that the petition under Section 11(6) was not maintainable as the statutory mechanism under the MSMED Act had not reached the arbitration stage and no independent arbitration agreement existed
¶ 35, 39The petition was dismissed; however, the Court directed the MSEF Council to finalize the pending conciliation proceedings and take further recourse within two months
¶ 40-41Original Court PDF
M/S Jubilant Marketing Pvt LtdvsM/S Robbins Tunneling And Trenchless Technology India Pvt Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
