01Facts
The parties entered into Agreement No. 02/EE/(Edu.) M (E&NE) PWD/2021-22 on 26 March 2022, which contained an arbitration clause at Clause 25.
pp. 1–2, 2–5The petitioner stated that it completed the contracted work and received a completion certificate dated 15 November 2025; disputes later arose concerning amounts allegedly payable under the agreement.
pp. 1–2After seeking resolution through communications to the respondent, the petitioner issued notices dated 27 May and 25 June 2026 invoking arbitration and seeking appointment of an arbitrator. The respondent rejected the petitioner’s claims on 15 July 2026.
p. 2The petitioner then filed this petition under Sections 11(5) and 11(6) of the Arbitration and Conciliation Act, 1996. The respondent accepted notice, and the parties agreed to refer the disputes to arbitration.
p. 602Issues
i.Whether a valid arbitration agreement existed between the parties.
¶ 11 · p. 6ii.Whether the Court should appoint a sole arbitrator to adjudicate the disputes.
¶ 12–13 · p. 603Law Applied
Under Sections 11(5) and 11(6) of the Arbitration and Conciliation Act, 1996, the Court’s enquiry at the appointment stage is confined to determining the prima facie existence of an arbitration agreement.
¶ 10 · p. 6The Court relied on SBI General Insurance Co. Ltd. v. Krish Spinning, 2024 SCC OnLine SC 1754, for this principle.
¶ 10 · p. 6Clause 25 of the parties’ agreement provided for arbitration of disputes arising out of or relating to the contract.
pp. 2–5The appointed arbitrator was required to furnish the disclosures contemplated by Section 12(2) of the Act.
¶ 14 · p. 7Provisions in the judgment · 4 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 11Section 21Section 76Section 12
04Reasoning
The Court found no dispute regarding the existence of a valid arbitration clause and noted that the parties were ad idem on referring their disputes to arbitration.
¶ 11–12 · p. 6Applying the limited prima facie enquiry under Section 11, it found no impediment to appointing a sole arbitrator.
¶ 10, 12–13 · p. 6It left all pleas, including objections to arbitrability and jurisdiction, open for determination by the arbitrator.
¶ 16 · p. 705Holding
The petition was disposed of by appointing Mr. Sarvagya Kumar Srivastava, Retd. Engineer-in-Chief, Delhi, PWD (Special Director General, CPWD), as sole arbitrator.
¶ 13–15 · pp. 6–7The arbitrator was directed to enter upon the reference within three weeks and furnish the requisite Section 12(2) disclosures; the arbitration was to be conducted under the aegis of the Delhi International Arbitration Centre (DIAC), with fees as per its Schedule of Fees.
¶ 13–15 · pp. 6–7The arbitrator was to decide the disputes independently and on their merits, without being influenced by the Court’s observations.
¶ 17 · p. 7Original Court PDF
M/S K L Arora Construction Pvt LtdvsPublic Works Department
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
