Delhi High CourtArbitration and MediationContract Law

Section 11 Judicial Scrutiny is Confined to Prima Facie Examination of Arbitration Agreement's Existence

Subhash Chanderv.Delhi Development Authority, Through Executive Engineer

Section 11 Judicial Scrutiny is Confined to Prima Facie Examination of Arbitration Agreement's Existence. Subhash Chander vs Delhi Development Authority, Through Executive Engineer. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Court should appoint an arbitrator under Section 11 when disputes have arisen and the arbitration clause existence is not in doubt.

The court held

The Court held that the scope of Section 11 is "extremely circumscribed" and limited to the prima facie existence of a valid agreement.

It also directed

The Court allowed the petition and appointed Mr. Ganesh Chandra Kabi (Engineer) as the Sole Arbitrator.

The Arbitrator was directed to furnish disclosures under Section 12(2) and follow the fee structure of the Fourth Schedule of the Act.

All rights and contentions on merits were left open for the Arbitrator’s determination.

01Facts

The Petitioner approached the High Court of Delhi under Section 11 of the Arbitration and Conciliation Act, 1996, seeking the appointment of a Sole Arbitrator to adjudicate disputes arising from an Agreement dated 10.12.2022.

p. 1

The Agreement contained Clause 25, which mandated a two-tier dispute resolution process: initial reference to a Dispute Redressal Committee (DRC) followed by arbitration if the DRC failed to decide or if a party remained dissatisfied.

p. 2

The Petitioner issued a Section 21 notice on 03.11.2025.

pp. 4-5

The Respondent raised certain objections in a counter-affidavit but conceded that these could be urged before the Arbitrator given the court’s limited jurisdiction under Section 11.

p. 5

02Issues

i.1. Whether the Court should appoint an arbitrator under Section 11 when disputes have arisen and the arbitration clause existence is not in doubt.

p. 5 · ¶ 4

ii.2. What is the scope of judicial scrutiny under Section 11(6) of the Arbitration and Conciliation Act, 1996, in light of recent Supreme Court precedents?

p. 5 · ¶ 5

03Law Applied

Section 11 of the Arbitration and Conciliation Act, 1996, regarding the appointment of arbitrators.

p. 1

Judicial intervention under Section 11 is confined strictly to a prima facie examination of the existence of the arbitration agreement.

p. 6 · ¶ 113

The "negative effect of competence-competence" requires that issues such as "accord and satisfaction" or "ex-facie meritless" claims be left to the Arbitral Tribunal under Section 16.

p. 7 · ¶ 119 · p. 8 · ¶ 121

Provisions in the judgment · 8 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 7Section 8Section 11Section 12Section 16Section 21Section 37Section 4

04Reasoning

The Court observed that since the parties were ad idem regarding the existence of the arbitration clause (Clause 25) and the necessity of referring the dispute to a Sole Arbitrator, the statutory requirements were met.

p. 5, 9

Applying the Krish Spinning standard, the Court held that its role is facilitative and procedural, intended only to resolve deadlocks in the appointment process without embarking on an adjudication of contentious facts or law.

p. 9 · ¶ 6

The Court noted that the Respondent's objections in the counter-affidavit were preserved but must be addressed by the Arbitral Tribunal, as the court must not conduct a "laborious enquiry" at this nascent stage.

p. 5 · ¶ 3-4 · p. 6 · ¶ 114

The Court also respected the specific contractual requirement in Clause 25 that the arbitrator must be a Graduate Engineer of a certain rank.

p. 9 · ¶ 9

05Holding

The Court held that the scope of Section 11 is "extremely circumscribed" and limited to the prima facie existence of a valid agreement.

p. 9, para 7

The Court allowed the petition and appointed Mr. Ganesh Chandra Kabi (Engineer) as the Sole Arbitrator.

p. 10 · ¶ 11

The Arbitrator was directed to furnish disclosures under Section 12(2) and follow the fee structure of the Fourth Schedule of the Act.

p. 10 · ¶ 12-13

All rights and contentions on merits were left open for the Arbitrator’s determination.

p. 10 · ¶ 15
Delhi High Court

Original Court PDF

Subhash ChandervsDelhi Development Authority, Through Executive Engineer

Delhi High Court · April 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment