Facts
The Delhi Electricity Regulatory Commission (Review Petitioner) sought a review of the Tribunal's order dated 20th April 2026. That order had quashed the Lt. Governor’s approval to entrust the audit of Delhi Discoms (Respondents 31-33) to the Comptroller and Auditor General (CAG)
Source reference: p. 9The Tribunal had instead directed the Commission to appoint a private chartered accountant for a "strict and intensive audit" as mandated by a Supreme Court RA judgment dated 6th August 2025
Source reference: p. 9The Commission argued that previous interim orders dated 11th February 2026 and 26th September 2025 had impliedly permitted a CAG audit
Source reference: p. 10The Commission requested an extension of time to appoint an auditor and sought to delay the commencement of the liquidation of regulatory assets (valued at ₹38,552 crores) until July 2026
Source reference: p. 16-17Issues
1. Whether the Tribunal’s prior interim orders constituted an approval for the Commission to conduct the special audit through the CAG.
Source reference: p. 122. Whether the Tribunal lacked jurisdiction under Section 121 of the Electricity Act, 2003, to decide on the entrustment of the audit to the CAG.
Source reference: p. 133. Whether the Commission should be granted an extension to appoint a chartered accountant and a delay in commencing the liquidation of regulatory assets.
Source reference: p. 16-17Law Applied
Section 121 of the Electricity Act, 2003, which empowers the Tribunal to issue orders/instructions to Regulatory Commissions for the performance of statutory functions, provided it does not involve adjudicating a pending dispute before the Commission itself
Source reference: p. 14Section 21 of the CAG (DPC) Act, 1971, to hold that a CAG audit of private Discoms was legally impermissible in this context
Source reference: p. 15Precedent of Andhra Pradesh State Load Despatch Centre v. M/s KSK Mahanadi Power Company Ltd. regarding the scope of Section 121 power
Source reference: p. 13-14Electricity Regulatory Commission (Appointment of Consultants) Regulations, 2001 regarding the procedural timeframe for hiring auditors
Source reference: p. 16Reasoning
The Tribunal rejected the Commission's interpretation of previous orders, clarifying that merely recording a submission or refraining from an early examination of an issue does not constitute legal approval
Source reference: p. 12Regarding jurisdiction, the Tribunal held that it was acting under the Supreme Court's mandate to monitor the audit process; therefore, it was duty-bound to ensure that the Commission’s actions complied with statutory limits, such as Section 21 of the CAG Act
Source reference: p. 15The Tribunal noted that failing to intervene when a Commission contravenes statutory provisions would violate the spirit of Section 121
Source reference: p. 15Regarding the regulatory assets, the Tribunal observed that since the assets are massive (₹38,552 crores), any delay causes undue prejudice to consumers, and the "true-up" process for FY 2023-24 is not a valid legal impediment to starting liquidation
Source reference: p. 18-19Holding
The Tribunal dismissed the Review Petitions, finding no manifest error in the original order
For Review Petition 7/2026, the Tribunal granted a limited extension of 45 days (from the original one week) to complete the appointment of a chartered accountant, citing mandatory consultant appointment regulations
Source reference: p. 17For Review Petition 8/2026, the Tribunal refused to modify the direction to liquidate regulatory assets and ordered the process to commence positively by 16th June 2026
Source reference: p. 19Original Court PDF
Delhi Electricity Regulatory CommissionvsForum of Regulators Central Electricity Regulatory Commission & Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in