01Facts
The parties executed an Agreement to Sell dated 17 January 2022 for land in Village Gadaipur, Delhi, for ₹22 crore. The agreement addressed several parcels, including land dependent on family settlements; Clause 6 specified 31 March 2022 as a deadline, while Clause 7 referred to a further parcel without stating a separate date
pp. 2–4 · ¶ 2(i), 2(iii), 13After some conveyances and payments, the petitioner sought further conveyance of the remaining land following a 2024 deed of exchange, invoked arbitration, and sought specific performance. The arbitrator dismissed that claim but directed refund of ₹97 lakh with interest and costs
pp. 5–8 · ¶ 2(viii)–(xi), 3The petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, and sought interim restraint under Section 9
pp. 8–12 · ¶ 4, 602Issues
i.Whether the arbitral award disclosed a ground under Section 34 or Section 34(2A), including patent illegality or contravention of fundamental policy, warranting interference
pp. 15–21 · ¶ 9–12ii.Whether the arbitrator’s construction of Clauses 2, 6 and 7—particularly the application of the 31 March 2022 deadline to the agreement as a whole—was a permissible interpretation
pp. 29–35 · ¶ 23–30iii.Whether the arbitrator’s finding that the petitioner failed to establish readiness and willingness under Section 16(c) of the Specific Relief Act, 1963, was open to challenge under Section 34
pp. 38–47 · ¶ 35–47iv.Whether the petitioner’s Section 9 application remained necessary after dismissal of the Section 34 challenge
pp. 8, 48–49 · ¶ 4–5, 5303Law Applied
Section 34 of the Arbitration and Conciliation Act permits only limited review of an arbitral award; a court cannot reappreciate evidence or substitute its interpretation where the arbitrator has adopted a plausible view, and patent illegality must go to the root of the matter [*MMTC Ltd. v. Vedanta Ltd.*, (2019) 4 SCC 163; *OPG Power Generation (P) Ltd. v. Enexio Power Cooling Solutions (India) (P) Ltd.*, (2025) 2 SCC 417].
pp. 15–21 · ¶ 10–12An arbitrator may interpret a contract but cannot rewrite it; a reasonable contractual interpretation is ordinarily not reviewable under Section 34.
p. 29 · ¶ 23Under Section 16(c) of the Specific Relief Act, a claimant seeking specific performance must aver and prove performance, or continuous readiness and willingness, to perform essential contractual terms; readiness concerns capacity, including financial capacity, while willingness is assessed from conduct [*His Holiness Acharya Swami Ganesh Dassji v. Sita Ram Thapar*, (1996) 4 SCC 526].
pp. 44–46 · ¶ 42–46The 2018 amendment to the Specific Relief Act narrowed the former general equitable discretion to refuse specific performance, but the statutory bar in Section 16(c) remains applicable.
pp. 39–44 · ¶ 39–43Provisions in the judgment · 22 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 9 provisions
Section 9Section 11Section 17Section 28Section 34Section 37Section 48Section 75Section 81Bharatiya Sakshya Adhiniyam, 2023 Section 65
Indian Contract Act, 1872 Section 25Section 32Section 35
Indian Penal Code, 1860 Section 24Section 25Section 463Section 464
Registration Act, 1908 Section 17Section 49
Specific Relief Act, 1963 Section 13Section 16Section 20
04Reasoning
The Court held that the arbitrator had addressed the challenge to the ATS’s authenticity and consideration, and that the record did not show an abdication of the duty to decide the framed issues.
pp. 24–29 · ¶ 15–22It found the interpretation applying the 31 March 2022 deadline to Clauses 6 and 7 to be a plausible reading of the agreement; the post-deadline payments and conveyances related to the Clause 6 parcel and did not establish waiver as to the Neeta Anand parcel.
pp. 29–37 · ¶ 23–34On readiness and willingness, the Court found that the arbitrator had considered the petitioner’s conduct and financial evidence. The certificates and other material did not establish readily deployable funds for the transaction, and the Court declined to reweigh that evidence.
pp. 45–47 · ¶ 45–47The award therefore disclosed no reviewable ground under Section 34; with that challenge dismissed, the interim Section 9 application had become infructuous.
pp. 48–49 · ¶ 49–5305Holding
The Court dismissed the Section 34 petition, leaving intact the award’s dismissal of specific performance and its direction that the respondent refund ₹97 lakh with interest and pay ₹25 lakh in costs.
pp. 6–8, 48–49 · ¶ 3, 48, 52–53It disposed of the Section 9 petition as infructuous.
p. 49 · ¶ 53Original Court PDF
Sanjeev SinghalvsShefali Varma
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
