01Facts
The dispute pertains to a group housing project, "Antriksh Sanskriti," in Ghaziabad
¶ 3, 5In 2006, the land-owning Society initially engaged the Appellant for development, but due to financial constraints, a tripartite Collaboration Agreement was executed on 09.02.2010, inducting Respondent No. 1 as the subsequent developer
¶ 3-5The agreement capped Respondent No. 1’s liability for statutory dues at ₹11 Crores
¶ 6Disputes arose regarding the liability for additional statutory payments to the Ghaziabad Development Authority (GDA), project delays, and site sealing
¶ 7-9In arbitration, the Appellant’s claims of ₹710 Crores were rejected, while Respondent No. 1’s counterclaims were partially allowed to the extent of ₹12,01,01,524/-, including a ₹9 Crore claim for "financial assistance" provided to the Appellant
¶ 10-11The Appellant challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 ("the Act"), which was dismissed by a Single Judge on 10.05.2024
¶ 1, 12The Appellant subsequently filed this appeal under Section 37 of the Act.
02Issues
i.1. Whether the Single Judge failed to exercise jurisdiction under Section 34 of the Act by not adequately examining grounds of patent illegality and perversity
¶ 24(i)ii.2. Whether the Arbitral Tribunal’s finding on limitation regarding the counterclaims was ex-facie contrary to law
¶ 24(ii)iii.3. Whether the award suffered from a total absence of evidence regarding the allowed counterclaims, specifically the ₹9 Crore financial assistance
¶ 24(iii)iv.4. Whether the Arbitrator’s interpretation of the Collaboration Agreement regarding the allocation of statutory dues constituted a plausible view
¶ 24(iv)03Law Applied
The court applied Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, which restrict judicial interference to grounds of patent illegality, perversity, or jurisdictional error, prohibiting a merits-based review or re-appreciation of evidence
¶ 25, 32It relied on Section 19(4) of the Act, which empowers the Arbitral Tribunal to determine the admissibility and weight of evidence without being strictly bound by the Indian Evidence Act, 1872
¶ 42Regarding limitation, it applied the Supreme Court's directions in In Re: Cognizance for Extension of Limitation (Suo Motu W.P. (C) No. 3/2020) concerning the COVID-19 pandemic
¶ 35Furthermore, it applied the evidentiary principle from Rajinder Pershad v. Darshana Devi, holding that failure to cross-examine a witness on a crucial point leads to an inference that the testimony is admitted
¶ 38-39Provisions in the judgment · 3 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 34Section 37Section 19
04Reasoning
The Court observed that its jurisdiction under Section 37 is limited to ensuring the Section 34 court did not overlook patent illegalities
¶ 25Regarding contractual interpretation, the Arbitrator’s distinction between statutory dues (capped at ₹11 Cr) and construction costs was found to be a "plausible view" arising from the Collaboration Agreement; therefore, the Court refused to substitute its own interpretation
¶ 30-32On the issue of limitation, the Court upheld the Tribunal’s reliance on the Supreme Court’s COVID-19 extension orders, noting that since the Tribunal applied a legally sustainable exclusion, the finding was not ex-facie illegal
¶ 35-36Concerning the "no evidence" plea for the ₹9 Crore counterclaim, the Court found that the Appellant had failed to specifically deny the receipt of funds in its pleadings and had not cross-examined the Respondent's witness (RW-2) on this point
¶ 37, 39Under Section 19(4), the Arbitrator was entitled to weigh this lack of rebuttal as sufficient evidence. The Court concluded that the Appellant’s challenge was merely a request for re-appreciation of the weight of evidence, which is impermissible under Section 37
¶ 40-4205Holding
The High Court dismissed the appeal, holding that the Single Judge correctly applied the parameters of Section 34
¶ 47-48The Court held that the Arbitral Award was based on a plausible interpretation of the contract and unrebutted evidence, and did not suffer from patent illegality, perversity, or jurisdictional error
¶ 44, 46The counterclaims were held to be within time due to the Supreme Court’s pandemic-related limitation extensions
¶ 35The Impugned Judgment of the Single Judge was affirmed
¶ 48Original Court PDF
Proto Developers And Technologies LtdvsM/S Antriksh Realtech Pvt Ltd & Anr.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
