Gauhati High Court

Section 37 jurisdiction precludes interference with an Arbitral Tribunal’s plausible interpretation of contractual clauses.

Indian Oil Corporation (Bongaigaon Refinery), vs M/S Esteem Projects Pvt. Ltd.,

Gauhati High CourtJUDGMENT: April 20, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant awarded a contract for the "Heater package for the DHDT project" to the Respondent on 16.08.2007, with a scheduled completion period of 13 months.

Source reference: p.2-3

The work was completed on 10.08.2011, following a delay of 1059 days.

Source reference: p.3

The Respondent submitted its final running account (RA) bill on 19.04.2012.

Source reference: p.3

On 20.08.2014—more than two years after the final bill submission—the Appellant granted a post-facto extension of time but imposed Liquidated Damages (LD) of 10% of the contract value (Rs. 2,59,57,700/-).

Source reference: p.3

The Respondent initiated arbitration, where the Arbitral Tribunal (AT) ordered the refund of the LD amount and payment of the RA bill, while rejecting other claims as "non-notified".

Source reference: p.5-6

The District Judge, Chirang, dismissed the challenge on 26.02.2019.

Source reference: p.7-8
02

Issues

1. Whether the dispute regarding the deduction of Liquidated Damages (LD) was a "non-arbitrable" dispute because it was not "notified" by the contractor in accordance with Clause 6.6.1.0 and 9.1.0.0 of the General Conditions of Contract (GCC).

Source reference: para. 16-17

2. Whether the Arbitral Tribunal and the Section 34 Court erred in interpreting the contract to allow jurisdiction over a claim that was not included in the final bill.

Source reference: para. 18-21

3. Whether the scope of appellate interference under Section 37 permits the Court to substitute its own interpretation of contract clauses for a "plausible" view taken by the Arbitral Tribunal.

Source reference: para. 27, 39
03

Law Applied

Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, which limit judicial interference in arbitral awards to specific grounds like patent illegality or perversity.

Source reference: p.2, 20

Clause 6.6.1.0 (requirement for written notice of claims within 10 days) and Clause 9.1.0.0 (referability of notified claims and owner-made deductions to arbitration) of the General Conditions of Contract (GCC).

Source reference: p.16-19

The court relied on the precedent in UHL Power Company Limited v. State of Himachal Pradesh (2022) and Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd. (2019), which establish that courts must defer to an Arbitral Tribunal’s interpretation of a contract if it is a plausible view, even if an alternative interpretation exists.

Source reference: p.20-21
04

Reasoning

The Appellant contended that under Clause 9.1.0.0, only "notified claims" included in the final bill are referable to arbitration; since the LD challenge was not notified within 10 days of the occurrence, the AT lacked jurisdiction.

Source reference: p.8-10

The Court rejected this, observing that the Appellant only decided to impose LD in 2014, roughly 2.5 years after the Respondent had submitted its final RA bill in 2012.

Source reference: p.17-18

Consequently, it was factually impossible for the Respondent to notify or include the LD dispute in the final bill.

Source reference: p.18-19

The Court further analyzed Clause 9.1.0.0, noting it contains two distinct parts: the first regarding "notified claims" of the contractor, and the second regarding disputes arising out of amounts "deducted from the final bill" by the Owner.

Source reference: p.18-19

The Court held that the LD deduction fell under the second part, which does not carry the same notification rigors as the first.

Source reference: p.18-19

Given the restrictive scope of Section 37, the Court found the Tribunal’s interpretation to be "possible and plausible" and not "unpardonably perverse".

Source reference: p.21-22
05

Holding

The Gauhati High Court dismissed the appeal, affirming the judgment of the District Judge, Chirang.

The Court held that the Arbitral Tribunal had proper jurisdiction to adjudicate the LD refund because the deduction occurred long after the final bill was submitted, exempting it from the standard notification requirements of Clause 6.6.1.0.

Source reference: p.18-19, 22

The court vacated the stay on the execution of the lower court's order and declared the Respondent entitled to pendente lite interest as per the original arbitral award.

Source reference: p.23
Gauhati High Court

Original Court PDF

Indian Oil Corporation (Bongaigaon Refinery),vsM/S Esteem Projects Pvt. Ltd.,

Gauhati High Court · April 20, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment