Facts
The petitioner claimed ownership through his deceased mother, Bibi Taslima, over land in Khata No. 228, Plot No. 1959, Thana No. 81, Mauza Harinkol, Bhagalpur.
Source reference: paras. 3–7; pp. 2–5Although approximately 0.37 acres of the land was acquired for the Pirpainti Thermal Power Project, compensation proceedings initially assessed and paid compensation only for 0.22 acres, leaving 0.15 acres unpaid.
Source reference: paras. 3–7; pp. 2–5Enquiries by the District Land Acquisition Officer and the project authorities subsequently confirmed that 0.37 acres fell within the acquired area and that the short assessment resulted from a measurement error.
Source reference: paras. 7–9; pp. 4–6After repeated representations and an earlier writ petition, the authorities assessed and paid the petitioner Rs. 20,14,200 on 27 August 2025, while disputes continued regarding the correct compensation and statutory interest.
Source reference: paras. 11–15; pp. 7–10The petitioner claimed a substantially higher amount, including compensation, solatium, 12% additional amount, and interest under Sections 30(3) and 80 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (“RFCTLARR Act”).
Source reference: paras. 15–20; pp. 10–12Issues
1. Whether the petitioner was entitled to compensation for the additional 0.15 acres acquired for the project, notwithstanding the initial payment made for only 0.22 acres
Source reference: paras. 7–12; pp. 4–92. Whether the amount payable under Section 30(3) of the RFCTLARR Act was to be calculated on the market value of the land together with the value of assets, but excluding the solatium amount
Source reference: paras. 22–26; pp. 13–163. Whether interest under Section 80 of the RFCTLARR Act was payable on the entire compensation amount, including solatium and the amount under Section 30(3), rather than only on the market value of the land
Source reference: paras. 27–31; pp. 16–194. What further amount remained payable after adjusting the amount already received by the petitioner
Source reference: paras. 31–35; pp. 18–20Law Applied
The Court applied Sections 26–30 of the RFCTLARR Act, 2013, under which the compensation computation includes the market value of the acquired land and the value of assets attached to it; solatium is then calculated on that compensation amount under Section 30(1).
Source reference: paras. 23–25; pp. 13–16The Court held that the additional amount/interest contemplated by Section 30(3) must be calculated on the market value of the land plus the value of attached assets, without adding solatium to that base.
Source reference: paras. 22–26; pp. 13–16Section 80 requires interest on compensation not paid or deposited before possession: 9% per annum for the first year and 15% per annum thereafter on the unpaid compensation.
Source reference: paras. 27–30; pp. 16–18The Court further interpreted “amount of such compensation” under Section 80 to include the total compensation payable, including solatium and the amount determined under Section 30(3).
Source reference: paras. 28–31; pp. 17–19Reasoning
The authorities’ enquiry established that 0.15 acres had been physically acquired and utilised for the thermal power project but had not initially been compensated due to a measurement mistake.
Source reference: paras. 7–12; pp. 4–9For the additional land, the Court accepted the land value of Rs. 2,85,000, applied the factor of two, and added Rs. 1,00,800 as the value of assets, producing a land-and-assets base of Rs. 6,70,800.
Source reference: para. 25; pp. 15–16It then calculated the Section 30(3) amount at Rs. 2,83,941, without including solatium in the interest base, and added solatium of Rs. 6,70,800 to the land-and-assets amount.
Source reference: paras. 25–26; pp. 15–16For Section 80, the Court rejected both the petitioner’s and the State’s calculations: the petitioner had improperly calculated the statutory amount by including solatium in the Section 30(3) base, while the State had confined Section 80 interest to the bare market value of the land.
Source reference: paras. 22–24, 27–30; pp. 13–18Since the full compensation had not been paid upon possession, the Court calculated Section 80 interest on Rs. 16,25,541, comprising compensation, solatium, and the Section 30(3) amount.
Source reference: para. 31; pp. 18–19Holding
The Court held that the petitioner was entitled to compensation for the unpaid 0.15 acres.
The total compensation was determined at Rs. 13,41,600, the Section 30(3) amount at Rs. 2,83,941, and Section 80 interest at Rs. 24,34,967, making a total of Rs. 40,60,508.
Source reference: paras. 26, 31; pp. 16, 18–19After adjusting the amount already treated as paid—Rs. 20,54,709—the District Land Acquisition Officer, Bhagalpur, was directed to pay Rs. 20,05,799 to the petitioner within two months.
Source reference: paras. 32–34; p. 19If payment was not made within that period, the State would be liable to pay penal interest at 12% per annum on the payable amount from 7 April 2015 until payment.
Source reference: para. 35; p. 20The writ petition was accordingly allowed.
Source reference: para. 37; p. 20Acts & Sections Cited
7 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 20137
Original Court PDF
Shekh KalimvsThe State of Bihar
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
