01Facts
The Petitioner Society entered into a Development Agreement (DA) in 2013 with the Respondent Developer for property redevelopment
¶ 2-3Following defaults in rent and construction, the Society filed a Section 9 petition in 2017, resulting in a "December 2017 Order" that attached the Developer’s personal assets and restrained them from creating third-party rights in any of their projects
¶ 4-5, 30-32Over the years, 31 Interim Applications (IAs) were filed by third-party decree-holders, allottees from unrelated projects, and the Developer's family members, seeking intervention or release of funds
¶ 1, 11-14An Arbitral Tribunal was finally constituted in September 2024, and a Section 17 order was passed in February 2026 regarding the same subject matter
¶ 5-702Issues
i.1. Whether a Section 9 Court should continue exercising jurisdiction and entertaining third-party interventions once an Arbitral Tribunal has been constituted
¶ 22, 25ii.2. Whether third parties (decree-holders and allottees of unrelated projects) have the standing to intervene in Section 9 proceedings arising from a specific arbitration agreement
¶ 27-28iii.3. Whether the restrictive "December 2017 Order" should be modified or referred to the Arbitral Tribunal for reconsideration
¶ 34-3903Law Applied
Section 9 is intended for the "preservation and protection" of the subject matter of the arbitration agreement
¶ 19Per Section 2(1)(h), a "party" is limited to those seeking relief under the arbitration agreement
¶ 20The court applied the "veritable parties" doctrine as established in Cox and Kings Ltd. v. SAP India (P) Ltd. and ASF Buildtech Pvt. Ltd. v. Shapoorji Pallonji, requiring a non-signatory to show proximity, consent, or a de facto connection to the dispute to be joined
¶ 27-28Under Section 9(3), once a tribunal is constituted, the Court shall not entertain applications unless Section 17 is inefficacious
¶ 19, 22Provisions in the judgment · 7 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 2Section 9Section 11Section 17Section 21Section 36Section 37
04Reasoning
The Court reasoned that Section 9 is not a "standalone equity jurisdiction" but is tethered to the arbitration agreement
¶ 21Since a Tribunal is now constituted and has passed a Section 17 order, the Section 9 proceedings must end to respect the "rule of law"
¶ 24-25Regarding third-party Applicants, the Court held they lacked privity; being a creditor of a developer does not make one a "veritable party" to an arbitration agreement in a bilateral contract
¶ 28, 49The Court found it "impermissible" for a Section 9 Court to conduct mini-trials or auctions for assets (like the Mahul Property) involving third-party claims
¶ 56Furthermore, continuing a blanket injunction (December 2017 Order) over all of the Developer's projects for nearly a decade was deemed a matter for the Tribunal to reassess based solely on the Society's specific claims in the Statement of Claim (SOC)
¶ 34-3705Holding
The Court disposed of the Section 9 Petition and all 31 IAs
¶ 71All third-party IAs are rejected as the applicants lack privity to the DA
¶ 48-51The "December 2017 Order" and the custody of deposited funds (approx. ₹11 crores) are referred to the Arbitral Tribunal, which must determine the "surplus" beyond the Society's needs within three months
¶ 38-40, 70(C)-(E)The Developer is held to his undertaking to pay third-party decree-holders within 12 months of the release of funds
¶ 43, 70(F)The private Court Commissioner is replaced by an official Registry Commissioner to facilitate a handover to the Tribunal
¶ 68-70Original Court PDF
Kalpana Pravin ShindevsMulund Raviraj Cooperative Housing Society Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
