Bombay High CourtArbitration and MediationCivil Procedure and Evidence

Section 9 jurisdiction is limited to preserving the arbitration agreement's subject matter and cannot settle unrelated third-party claims.

Mulund Raviraj Co-Operative Housing Society Ltd.v.Rupji Constructions And Anr

Section 9 jurisdiction is limited to preserving the arbitration agreement's subject matter and cannot settle unrelated third-party claims.. Mulund Raviraj Co-Operative Housing Society Ltd. vs Rupji Constructions And Anr. Bombay High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether a Section 9 Court should continue exercising jurisdiction after an Arbitral Tribunal has been constituted and an application under Section 17 has been filed.

The court held

The Court disposed of the Section 9 Petition and all 31 IAs

It also directed

all third-party interventions are rejected as they lack privity to the arbitration agreement

the Arbitral Tribunal shall determine within three months what portion of the deposited funds is necessary to secure the Society's claim; any surplus shall be released to the Developer

the Tribunal is empowered to vary or vacate the December 2017 injunction

the Court Commissioner is disbanded and replaced by an official Registry officer for a joint handover

Third-party decree-holders were granted liberty to approach appropriate execution forums, with the time spent here excluded for limitation purposes

01Facts

The Petitioner Society entered into a Development Agreement (DA) in 2013 with Respondent No. 1 (Developer) for redevelopment

¶ 3

The Developer defaulted on statutory dues, transit rent, and construction milestones, leading the Society to file a Section 9 petition under the Arbitration and Conciliation Act, 1996, in 2017

¶ 4-5

On December 14, 2017, the Court passed a wide-reaching injunction attaching the Developer’s personal assets and restraining them from creating third-party rights in any of their projects

¶ 5, 30-32

Over time, 31 Interim Applications (IAs) were filed, mostly by third-party decree-holders and allottees from unrelated projects seeking a share of the funds (~Rs. 11 crores) deposited in Court

¶ 6, 12-14

In September 2024, an Arbitral Tribunal was finally constituted, and Section 17 proceedings commenced

¶ 5, 7

02Issues

i.1. Whether a Section 9 Court should continue exercising jurisdiction after an Arbitral Tribunal has been constituted and an application under Section 17 has been filed.

¶ 22

ii.2. Whether third parties (decree-holders and allottees of unrelated projects) who are not signatories to the arbitration agreement can intervene or claim relief in a Section 9 petition.

¶ 20, 27-28

03Law Applied

The court primarily applied Section 9 and Section 17 of the Arbitration and Conciliation Act, 1996. Section 2(1)(h) defines a "party" strictly as a party to an arbitration agreement

¶ 20

Under Section 9(3), once a tribunal is constituted, the Court shall not entertain interim measures unless Section 17 is found to be inefficacious

¶ 19

The court further applied the "veritable party" doctrine established in Cox and Kings Ltd. v. SAP India (P) Ltd. and ASF Buildtech Pvt. Ltd. v. Shapoorji Pallonji, which requires a non-signatory to demonstrate proximity, consent, or a de facto connection to the specific dispute to be impleaded

¶ 27-28

Provisions in the judgment · 7 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 2Section 9Section 11Section 17Section 21Section 36Section 37

04Reasoning

The Court reasoned that Section 9 is a protective jurisdiction in aid of arbitration, not a standalone equity jurisdiction for the world at large

¶ 19-21

Since the Arbitral Tribunal was now functional and had already passed a Section 17 order, the "rule of law" required the Section 9 Court to cease its involvement, as there was no evidence that Section 17 was inefficacious

¶ 24-25

Regarding the third-party intervenors, the Court held they lacked privity to the DA and were not "veritable parties"; their claims originated from entirely distinct projects and contracts

¶ 28, 49

The Court noted that allowing them to "chase assets" in Section 9 proceedings regarding a bilateral contract would be coram non judice (without jurisdiction)

¶ 46, 54

05Holding

The Court disposed of the Section 9 Petition and all 31 IAs

¶ 71

all third-party interventions are rejected as they lack privity to the arbitration agreement

¶ 70(A)

the Arbitral Tribunal shall determine within three months what portion of the deposited funds is necessary to secure the Society's claim; any surplus shall be released to the Developer

¶ 70(C-D)

the Tribunal is empowered to vary or vacate the December 2017 injunction

¶ 70(E)

the Court Commissioner is disbanded and replaced by an official Registry officer for a joint handover

¶ 68, 70(G)

Third-party decree-holders were granted liberty to approach appropriate execution forums, with the time spent here excluded for limitation purposes

¶ 44, 50, 70(B)
Bombay High Court

Original Court PDF

Mulund Raviraj Co-Operative Housing Society Ltd.vsRupji Constructions And Anr

Bombay High Court · April 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment