Facts
The Petitioner, a construction company, filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim reliefs against the Respondents.
Source reference: para. 1The dispute arose from a Letter of Intent dated 07.06.2023 and a Tender Agreement regarding a construction project.
Source reference: para. 1The Petitioner sought to restrain the Respondents from acting on a termination notice dated 03.02.2025, prevent them from engaging third parties or altering the existing structure, and requested a direction for the Respondents to deposit approximately ₹5.10 crores to secure pending bills.
Source reference: para. 1During the hearing, both parties reached a consensus to refer the matter to a Sole Arbitrator rather than adjudicating the Section 9 petition on its merits.
Source reference: para. 2Issues
Whether the disputes arising from the Letter of Intent and Tender Agreement should be referred to a court-appointed Sole Arbitrator based on party consensus?
Source reference: para. 2, 5Whether the Section 9 petition for interim measures can be treated as an application under Section 17 before the newly appointed Arbitral Tribunal?
Source reference: para. 13Law Applied
The Court applied Section 9 of the Arbitration and Conciliation Act, 1996, which allows parties to seek interim measures before or during arbitral proceedings.
Source reference: para. 1It also gave effect to the party autonomy principle under Section 21 regarding the commencement of proceedings and Section 12(2) regarding mandatory disclosures by arbitrators.
Source reference: para. 4, 8Furthermore, it utilized the procedural efficiency of converting a Section 9 petition into a Section 17 application (interim measures by an Arbitral Tribunal) to ensure the Arbitrator determines the merits of the interim protection.
Source reference: para. 13Reasoning
The Court noted that both parties were ad idem regarding the appointment of an independent arbitrator to resolve their disputes, which were valued at approximately ₹6 crores.
Source reference: para. 2, 6By mutual agreement, the parties waived the statutory requirements for a formal Section 21 notice and the filing of a separate Section 11 petition for the appointment of an arbitrator.
Source reference: para. 4The Court identified the arbitration clauses in the Letter of Intent and the General Conditions of Contract (GCC) which established New Delhi as the venue.
Source reference: para. 3To avoid delay and preserve the interests of justice, the Court exercised its power to appoint a Senior Advocate as the Sole Arbitrator, leaving all substantive disputes, including jurisdictional objections, to be decided by the Tribunal.
Source reference: para. 5, 11, 14Holding
The Court disposed of the petition by appointing Mr. Parthiv K. Goswami, Senior Advocate, as the Sole Arbitrator.
The Court directed that the present Section 9 petition be treated as an application under Section 17 to be decided by the Arbitrator upon entering the reference.
Source reference: para. 13The Arbitrator is required to provide disclosures under Section 12 within one week, and fees are to be governed by the Fourth Schedule of the Act, shared equally by the parties.
Source reference: para. 8-10No opinion was expressed on the merits of the underlying dispute.
Source reference: para. 12Original Court PDF
M/s Starashiyana Construction Pvt Ltd v. M/s Mayar Health Resorts Ltd & Ors. [O.M.P.(I) (COMM.) 140/2025]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in