Bombay High Court
Arbitration and MediationCommercial and Corporate Law

Section 9 protection was refused where an unpaid instalment undermined the acquirer’s readiness and willingness to perform.

Sky One Airways Private Limited vs Nayan Arun Jagjivan,

Bombay High CourtJUDGMENT: October 05, 20263 MIN READSOURCE JUDGMENT
Section 9 protection was refused where an unpaid instalment undermined the acquirer’s readiness and willingness to perform.. Sky One Airways Private Limited vs Nayan Arun Jagjivan,. Bombay High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

On 9 May 2026, the parties executed a Binding Term Sheet for the Petitioner’s proposed acquisition of 100% of Respondent No. 4’s share capital, alongside an Addendum setting out specified funding obligations and pre-conditions.

Source reference: paras. 2–6; pp. 1–5

The Petitioner acquired 9.5% of the shares and asserted that it advanced approximately ₹23.45 crore toward the transaction; the Respondents maintained that the advances were loans under a separate Inter-Corporate Loan Agreement.

Source reference: paras. 29, 34–38; pp. 25–32

The Petitioner did not pay the additional ₹52.50 lakh instalment due by the thirtieth day under the Term Sheet.

Source reference: paras. 34–38; pp. 27–32

After Respondent No. 4 issued a termination notice and sought release of escrowed shares, the Petitioner disputed the termination and applied under Section 9 of the Arbitration and Conciliation Act, 1996, for interim protection of the shares and the proposed acquisition.

Source reference: paras. 34–38, 47; pp. 27–32, 37–38

Respondent No. 4 subsequently asked the Escrow Agent to maintain status quo over the escrowed shares.

Source reference: para. 47; pp. 37–38
02

Issues

1. Whether the Term Sheet and Addendum constituted binding obligations, and what funding obligations they imposed on the parties.

Source reference: paras. 27–31, 58; pp. 24–27, 44

2. Whether the ₹23.45 crore advanced by the Petitioner could be treated as performance of its obligations under the Term Sheet, and whether the unpaid ₹52.50 lakh instalment affected its claim to interim relief.

Source reference: paras. 32–38; pp. 27–32

3. Whether the Petitioner established a sufficient basis under Section 9 for interim or ad-interim protection of the escrowed shares, the wider acquisition, and Respondent No. 4’s business and assets.

Source reference: paras. 41–60; pp. 33–46
03

Law Applied

Section 9 of the Arbitration and Conciliation Act, 1996 empowers the Court to grant interim measures of protection in aid of arbitration; the applicant must establish that the relief sought is necessary to protect the claimed right and the subject matter of the dispute.

Source reference: paras. 42–43, 51

Sections 51–54 of the Indian Contract Act, 1872, concerning reciprocal promises, were considered in assessing whether one party’s performance depended on the other’s performance; the Court treated that question as dependent on the wording and sequence of the particular contractual obligations.

Source reference: paras. 42–43, 51

No judicial precedent was cited.

Source reference: no citation
04

Reasoning

The Court held that the Term Sheet was binding, but did not itself effect a completed, unconditional transfer of all shares: completion remained subject to due diligence, regulatory approvals, escrow and other pre-conditions, followed by the contemplated Definitive Agreements.

Source reference: paras. 27–29, 40, 58

The Addendum did not support either the Petitioner’s claim that its total contribution was limited to ₹20 crore or the Respondents’ claim that all funding was unconditionally due; the specified contributions remained subject to their respective terms and conditions.

Source reference: paras. 29–31, 51

The contemporaneous Loan Agreement and related communications supported the Respondents’ position that the ₹23.45 crore was advanced as loans, not as the ₹5 crore share purchase price.

Source reference: paras. 32–38, 50–51

Separately, the ₹52.50 lakh instalment was payable by the earlier of completion of due diligence or the thirtieth day, and the Petitioner had not shown that it paid that amount by the due date; its later offer to deposit it did not establish timely performance.

Source reference: paras. 32–38, 50–51

Although the parties’ performance and the validity of termination remained disputed, the Respondents’ later request to maintain status quo reduced the immediate risk to the escrowed shares.

Source reference: paras. 41–48, 56

The broader requested orders would also have constrained Respondent No. 4’s corporate and operational affairs without a sufficiently established right to immediate completion or control.

Source reference: paras. 59–60
05

Holding

The Court dismissed the Section 9 petition.

It declined the requested restraints over the shares, company and business assets, and the mandatory directions concerning additional shares, finding that the Petitioner had not established a sufficient basis for the interim protection sought.

Source reference: paras. 59–62; pp. 45–47

The Court clarified that its observations were confined to the Section 9 application, left all contentions open, and permitted the parties to seek appropriate interim or protective relief before the arbitral tribunal; there was no order as to costs.

Source reference: para. 62; p. 47
06

Acts & Sections Cited

5 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19961

Bombay High Court

Original Court PDF

Sky One Airways Private LimitedvsNayan Arun Jagjivan,

Bombay High Court · October 05, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment