Delhi High CourtArbitration and MediationContract Law

Self-serving claims for additional work unsupported by joint measurements or documentary evidence are legally unsustainable.

Nandini Enterprisingv.Rajasthan Co Operative Group Housing Society Ltd And Anr

Self-serving claims for additional work unsupported by joint measurements or documentary evidence are legally unsustainable.. Nandini Enterprising vs Rajasthan Co Operative Group Housing Society Ltd And Anr. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Arbitrator erred in rejecting the petitioner's claim of ₹2,58,78,656 for additional work on the grounds that it was unsubstantiated and improbable

The court held

The Court answered both issues in the negative, holding that the Arbitrator’s findings were based on a reasonable appraisal of the lack of evidence provided by the petitioner

It also directed

The Court held that the award did not suffer from perversity or patent illegality under Section 34 of the Act

The petition was dismissed, and the arbitral award dated 30.05.2024 was upheld

01Facts

The petitioner was awarded a contract by the respondent on 23.06.2017 for building repairs and painting at a total value of ₹48,00,000

pp. 1-2

The work was to be completed by 31.12.2017, but despite extensions until 01.03.2018, the deadline was not met due to slow progress and under-deployment of labor

¶ 2.1

The petitioner raised five Running Account (RA) bills totaling ₹59,37,023, against which the respondent paid ₹49,19,907 based on joint measurements

¶ 2.1

The respondent terminated the contract on 10.04.2019

¶ 2.2

Subsequently, the petitioner submitted a final (sixth) bill for ₹2,58,78,656, sparking a dispute

¶ 2.2

The Arbitral Tribunal dismissed the petitioner's claims on 30.05.2024, leading to the current challenge under Section 34 of the Arbitration and Conciliation Act, 1996

¶ 1, 2.2

02Issues

i.1. Whether the Arbitrator erred in rejecting the petitioner's claim of ₹2,58,78,656 for additional work on the grounds that it was unsubstantiated and improbable

pp. 4 / para. 7-9

ii.2. Whether the finding that the breach of contract was attributable to the petitioner was perverse or patently illegal

pp. 6 / para. 12-15

03Law Applied

Section 34 of the Arbitration and Conciliation Act, 1996, which limits judicial interference in arbitral awards unless the award is vitiated by patent illegality or perversity

p. 1, 6

Associate Builders v. Delhi Development Authority (2015) 3 SCC 49, which establishes that an award cannot be set aside for mere factual errors unless it is so irrational that no reasonable person could have arrived at such a conclusion

p. 3, 7

Contractual principles regarding "Joint Measurement" clauses (Clause 21) and the evidentiary requirement for proving additional work beyond the original scope of the Letter of Award

pp. 4-5

Provisions in the judgment · 1 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 34

04Reasoning

The Court observed that the petitioner sought over ₹2.5 crores on a ₹48 lakh contract without providing any documentary evidence of work variations or approval for additional items

¶ 7-10

The Court noted that Clause 21 required payments to be based on "joint measurements," yet the petitioner admitted no joint measurement register was maintained for the claimed additional work

¶ 11

The Arbitrator’s finding that the claim "inspired no confidence" was upheld as the petitioner failed to produce tax invoices or procurement bills for the alleged extra materials

¶ 9-10

Regarding the breach, the Court found the Arbitrator's conclusion plausible because the petitioner failed to prove the deployment of adequate labor as per Clause 17 and admitted to starting work five months after the allotment date

¶ 13-15

The Court emphasized that it cannot reassess evidence or interfere with factual findings unless they are perverse, which was not the case here

¶ 12

05Holding

The Court answered both issues in the negative, holding that the Arbitrator’s findings were based on a reasonable appraisal of the lack of evidence provided by the petitioner

¶ 11, 15

The Court held that the award did not suffer from perversity or patent illegality under Section 34 of the Act

¶ 15, 18

The petition was dismissed, and the arbitral award dated 30.05.2024 was upheld

¶ 18
Delhi High Court

Original Court PDF

Nandini EnterprisingvsRajasthan Co Operative Group Housing Society Ltd And Anr

Delhi High Court · May 25, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment