01Facts
The Appellant booked an apartment in the ‘NBCC Green View Apartments’ project in 2013 and received possession in 2019
p. 2 · ¶ 5-6In 2021, IIT Delhi declared the project structurally unfit for habitation
p. 2 · ¶ 7Consequently, the District Disaster Management Authority (DDMA) ordered NBCC (Respondent No. 1) to refund allottees with interest
p. 2 · ¶ 7In July 2022, NBCC issued a "Buy Back Offer" for only the principal amount, which the Appellant initially resisted
p. 3 · ¶ 8However, claiming financial distress after NBCC stopped paying rent, the Appellant executed an "Acceptance-cum-Declaration Memorandum" in February 2023, accepting a one-time full settlement of the principal amount and registration charges
p. 4 · ¶ 12Later, NBCC introduced a new policy offering other allottees the principal plus 6% interest and interior costs
p. 4 · ¶ 13The Appellant filed a Writ Petition seeking parity under this new policy, which was disposed of by a Single Judge on the grounds that the dispute was contractual and involved questions of fact
p. 5 · ¶ 15The Appellant challenged this via the present intra-court appeal.
02Issues
i.1. Whether the High Court, in the exercise of its writ jurisdiction under Article 226, should adjudicate a dispute arising from a settlement memorandum alleged to be signed under coercion
p. 7 · ¶ 23ii.2. Whether an allottee who has signed a "full and final settlement" can subsequently challenge a newer policy based on arbitrary classification without first proving the original settlement is invalid
p. 8 · ¶ 28-2903Law Applied
Article 226 of the Constitution of India is generally not the appropriate forum for resolving private contractual disputes or complex "disputed questions of fact" such as fraud or coercion
p. 5 · ¶ 15 · p. 9 · ¶ 29While the "State" must not act in a discriminatory or arbitrary manner under Article 14, the doctrine of promissory estoppel and claims of parity cannot be entertained in writ proceedings if they are contingent upon setting aside a previously executed bilateral settlement agreement
p. 8 · ¶ 28Provisions in the judgment · 1 · Linked ones open on LawLens
Limitation Act, 1963 Section 5
04Reasoning
The Court reasoned that once the Appellant executed the Memorandum and received the settlement amount, the contract was concluded
p. 7 · ¶ 24The Appellant’s grievance—that the Respondent’s subsequent policy was more favorable—could only be addressed if the Appellant first proved that his initial settlement was vitiated by fraud or coercion
p. 8 · ¶ 28The Court observed that such allegations of coercion are factual in nature and require an evidentiary trial, which is not feasible under writ jurisdiction
p. 9 · ¶ 29The Court further noted that no evidence of coercion was presented at the time the Memorandum was signed, and the Appellant only raised objections after discovering that subsequent allottees received better terms
p. 8 · ¶ 27Since the matter is essentially a civil dispute over a contract, the Single Judge was correct in refusing to exercise extraordinary jurisdiction
p. 9 · ¶ 2905Holding
The Court answered that the High Court cannot entertain this dispute under Article 226 as it involves disputed questions of fact regarding the validity of a contract
p. 9 · ¶ 29The Court dismissed the appeal, holding that the Impugned Order suffered from no infirmity and correctly reserved the Appellant's liberty to approach a competent Civil Court for relief. The appeal was dismissed with no order as to costs
p. 9 · ¶ 30Original Court PDF
Vinay Kumar GuptavsNational Buildings Construction Corporation And Anr
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
