Gauhati High Court
Property and Real Estate LawAdministrative and Public Law

Severance compensation under Section 23 thirdly requires proof of actual damage.

Syedur Rahman vs The State Of Asssam And Anr.

Gauhati High CourtJUDGMENT: September 02, 20263 MIN READSOURCE JUDGMENT
Severance compensation under Section 23 thirdly requires proof of actual damage.. Syedur Rahman vs The State Of Asssam And Anr.. Gauhati High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The appellant owned 4 Bigha 2 Katha 7 Lecha of land at Salbari, Bongaigaon, Assam. The State acquired 1 Bigha 1 Katha 5 Lecha for construction of a broad-gauge railway line between New Maynaguri and Jogighopa.

Source reference: para. 3

The Collector assessed the land at ₹1,20,000 per Bigha and awarded total compensation of ₹6,62,312, including compensation for structures and standing zirat.

Source reference: para. 4

The appellant sought a reference under Section 18 of the Land Acquisition Act, 1894, contending that the compensation was inadequate.

Source reference: para. 5

The Reference Court enhanced the land value to ₹6,00,000 per Bigha and awarded compensation with 6% interest, resulting in total enhanced compensation of ₹9,29,040.

Source reference: paras. 2, 14

In appeal under Section 54, the appellant additionally claimed compensation under Section 23, thirdly, alleging that the railway construction had severed the remaining land into two parts and caused waterlogging, rendering it unusable.

Source reference: paras. 6–7

The respondents denied any such damage and stated that waterways, bridges and road under-bridges had been provided to prevent waterlogging.

Source reference: paras. 8–10
02

Issues

Whether the appellant was entitled to additional compensation under Section 23, thirdly, of the Land Acquisition Act, 1894, for alleged damage caused by severance of his remaining land due to the acquisition.

Source reference: paras. 6–7

Whether the Reference Court erred in failing to award compensation for alleged waterlogging and damage to the severed land and standing zirat.

Source reference: paras. 8–16

Whether the impugned judgment dated 4 February 2021 required interference in an appeal under Section 54 of the Land Acquisition Act, 1894.

Source reference: paras. 2, 18–19
03

Law Applied

The Court applied Section 54 of the Land Acquisition Act, 1894, which provides the appellate remedy against an award or judgment of the Reference Court.

Source reference: no citation

It further applied Section 23, thirdly, which requires consideration of damage sustained by an interested person, at the time of the Collector’s taking possession, by reason of severing the acquired land from the person’s other land.

Source reference: no citation

The governing principle was that compensation for severance or consequential damage must be supported by evidence establishing actual damage; a mere apprehension of waterlogging or reduced utility is insufficient.

Source reference: no citation

The Court also recognised that compensation for structures and zirat, solatium and additional compensation had already been awarded and paid.

Source reference: paras. 16–17
04

Reasoning

The Court found that the appellant’s principal contention before the Reference Court had been the inadequacy of the land valuation, which had already been enhanced from ₹1,20,000 to ₹6,00,000 per Bigha.

Source reference: para. 14

As regards severance damage, the appellant relied on the apprehension that the elevated railway track would cause rainwater to submerge the remaining land.

Source reference: para. 15

However, the Union of India had specifically stated that railway bridges and three road under-bridges had been provided to ensure adequate waterways and prevent waterlogging, and represented that the railway line had been constructed accordingly.

Source reference: paras. 9–10, 15

The Court held that there was no evidence demonstrating that the remaining land had in fact suffered waterlogging or other damage because of the acquisition.

Source reference: para. 16

Consequently, the statutory requirement for awarding compensation under Section 23, thirdly, was not established.

Source reference: no citation

The appellant had also received compensation for structures, zirat, solatium and additional compensation.

Source reference: para. 17
05

Holding

The Court answered the issues against the appellant and held that no additional compensation was payable under Section 23, thirdly, because actual severance-related damage had not been proved.

Finding no error or infirmity in the Reference Court’s judgment, the Court dismissed the appeal.

Source reference: paras. 18–19

The enhanced compensation awarded by the Reference Court remained undisturbed; the records were directed to be returned to the District Judge, Bongaigaon, and the parties were left to bear their own costs.

Source reference: paras. 20–21
06

Acts & Sections Cited

3 provisions across 1 statute referred to in this judgment. Linked provisions open on LawLens.

Land Acquisition Act, 18943

Section 54Section 18Section 23
Gauhati High Court

Original Court PDF

Syedur RahmanvsThe State Of Asssam And Anr.

Gauhati High Court · September 02, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment