01Facts
Appellant No. 1 (Bobble Keyboard) and its CEO (Appellant No. 2) entered into a Series C Shareholders Agreement (SHA) and other definitive agreements with the Respondent (Affle India) in 2020-2021.
¶ 3-7Clause 3.4 of the SHA granted "Major Investors" holding at least 8% shareholding the right to inspect the company’s offices, material contracts, and financial records.
¶ 96Disputes arose regarding ad monetization, revenue transparency, and alleged unauthorized share transfers by the Appellants.
¶ 10-13Respondent initiated SIAC arbitration (seated in New Delhi) and sought interim inspection rights under Section 17 of the Arbitration and Conciliation Act, 1996.
¶ 15, 19On 11.03.2024, the Sole Arbitrator granted interim relief, allowing the Respondent to exercise inspection rights subject to the execution of a Non-Disclosure Agreement (NDA) and Confidentiality Undertakings.
¶ 20The Appellants challenged this order under Section 37(2)(b), while the Respondent sought its enforcement under Section 17(2).
¶ 1, 2102Issues
i.1. Whether the scope of judicial interference under Section 37(2)(b) of the 1996 Act allows the Court to substitute the Arbitral Tribunal's plausible view with its own?
¶ 65-66ii.2. Whether the interim relief of inspection granted by the Tribunal amounted to granting the final relief sought in the Statement of Claim?
¶ 68-71iii.3. Whether the SHA is a "determinable" contract under Section 14(d) of the Specific Relief Act (SRA), thereby barring the grant of specific performance or interim mandatory injunctions?
¶ 73-78iv.4. Whether a contractual right to inspection falls within the ambit of "interim measures" under Section 17(1)(ii) of the 1996 Act?
¶ 83-8603Law Applied
The Court applied the restrictive standard of Section 37 of the Arbitration and Conciliation Act, 1996, as established in Ramesh Kumar Jain v. Bharat Aluminium Co. Ltd., holding that interference is warranted only if the order is perverse, arbitrary, or ignores settled law.
¶ 65Regarding the Specific Relief Act, 1963, the Court applied Section 14(d) but distinguished "determinable" contracts by relying on DLF Home Developers Limited v. Shipra Estate Limited, which stipulates that contracts containing express clauses for specific performance (such as Clause 14.10 of the subject SHA) are not determinable in nature.
¶ 78-79The Court further utilized the precedent in Ares Investment LLC v. International Print-O-PAC Ltd. to affirm that a contractual right to audit/inspect records constitutes a valid subject for interim protection under Section 17(1)(ii)(e).
¶ 85-87Provisions in the judgment · 10 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 9Section 17Section 34Section 37
Specific Relief Act, 1963 Section 14
Companies Act, 2013 Section 59Section 241Section 242Section 430
Code of Civil Procedure, 1908 Section 21
04Reasoning
The Court observed that its jurisdiction under Section 37 is narrow and co-extensive with Section 34 parameters; it cannot re-assess evidence or interfere with a Tribunal’s plausible interpretation of a contract.
¶ 65-67It rejected the Appellants' argument that the interim relief was identical to the final relief, noting that the final claim sought a declaration of breach, whereas the interim order provided a restricted, supervised inspection contingent upon NDAs.
¶ 71On the SRA challenge, the Court held that Clause 14.10 of the SHA explicitly made the agreement specifically enforceable, overriding the "determinable" bar under Section 14(d).
¶ 77-79It also dismissed the Section 14(b) objection regarding "continuous supervision," finding the Arbitrator’s oversight of the inspection was limited to a pre-trial window.
¶ 81-82The Court upheld the Tribunal’s application of the Section 17 "triple test," agreeing that the Respondent established a prima facie case via a literal reading of Clause 3.4 and that balance of convenience favored the Respondent’s need to holistically present its case in arbitration.
¶ 95-97, 104-105Confidentiality concerns were deemed mitigated by the mandatory NDAs.
¶ 10705Holding
The High Court dismissed the appeal and upheld the Arbitrator's order dated 11.03.2024, finding no perversity or manifest illegality.
¶ 118The Court held that the Respondent had a clear contractual right to inspection which could be protected as an interim measure.
¶ 117Regarding the enforcement petition (OMP (ENF.) (COMM) 66/2024), the Court directed the Appellants to comply with the inspection directions within four weeks.
¶ 123Original Court PDF
Talent Unlimited Online Services Private Limited And AnrvsAffle India Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
