Rajasthan High Court

State Commissions possess statutory competence to levy cost-reflective Parallel Operation Charges on Captive Power Plants.

HINDUSTAN ZINC LIMITED vs RAJASTHAN ELECTRICITY REGULATORY COMMISSION

Rajasthan High CourtJUDGMENT: June 19, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner, a company operating Captive Power Plants (CPPs), challenged the constitutional validity and statutory vires of Regulation 32 (Late Payment Surcharge/LPS) and Regulation 92 (Parallel Operation Charges/POC) of the RERC (Terms and Conditions for Determination of Tariff) Regulations, 2025.

Source reference: p. 2

The respondent-Commission published draft regulations on 23.11.2024, invited objections, and conducted a public hearing on 27.12.2024.

Source reference: p. 2-3

The petitioner contended that the POC was unauthorized by the Electricity Act, 2003, and that the LPS of 0.1% per day was arbitrary and punitive.

Source reference: p. 3-9

The final regulations were notified on 06.03.2025.

Source reference: p. 3
02

Issues

1. Whether Regulation 92 (POC) is ultra vires Sections 9 and 42 of the Electricity Act, 2003, by imposing a fiscal burden on Captive Power Plants not contemplated by the parent statute.

Source reference: p. 4, 19

2. Whether the Commission failed to comply with the mandatory procedure of "considering" objections under Section 181(3) of the Electricity Act and Rule 3 of the Electricity Rules, 2005.

Source reference: p. 6, 18

3. Whether Regulation 32 (LPS) is manifest arbitrary, disproportionate, and violative of Article 14 of the Constitution.

Source reference: p. 9, 23
03

Law Applied

Sections 61, 86, and 181 of the Electricity Act, 2003, which grant the State Commission broad powers to determine tariff and frame regulations consistent with the Act.

Source reference: p. 16-17

The principle from Transmission Corporation of Andhra Pradesh Ltd. v. Rain Calcining Ltd. (2021), which establishes that Grid Support Charges are leviable as the grid acts as a "cushion" and determining such technical charges is within the expert body's domain.

Source reference: p. 20-22

Hindustan Zinc Ltd. v. RERC (2016) regarding the limited scope of judicial review over policy choices of a statutory regulator.

Source reference: p. 10, 17

Rule 3 of the Electricity (Procedure for Previous Publication) Rules, 2005, holding that "consideration" of objections does not require a reasoned adjudicatory order for every individual stakeholder objection.

Source reference: p. 18
04

Reasoning

The Court reasoned that Regulation 92 (POC) is not a tax or penalty but a compensatory, cost-reflective charge for grid-support services utilized by CPPs synchronized with the grid.

Source reference: p. 13, 20

It found that Sections 9 and 42 of the Act do not expressly prohibit the Commission from determining such ancillary charges under its broader regulatory mandate.

Source reference: p. 19-20

Regarding the procedure, the Court held that the Commission’s consultation process—publishing drafts, inviting objections, and issuing a Statement of Objections and Reasons (SOR)—constituted sufficient statutory compliance; the regulator is not a quasi-judicial body required to provide individual findings for every objection.

Source reference: p. 18-19

On Regulation 32, the Court found the 0.1% daily LPS was a policy tool to maintain financial discipline and prevent distribution licensees from being used as interest-free credit sources, thus falling within the "commercial principles" of Section 61.

Source reference: p. 23-24

The Court declined to interfere with technical assessments based on the ERDA study, noting that the petitioner failed to prove manifest arbitrariness.

Source reference: p. 14, 25
05

Holding

The Court answered all issues in the negative and dismissed the writ petition.

It held that both Regulation 32 and Regulation 92 were within the legislative competence of the Commission and did not violate Articles 14 or 19(1)(g) of the Constitution.

Source reference: p. 24-25

The Court affirmed that it would not substitute its opinion for that of a specialized regulatory authority in matters of tariff fixation and technical cost determination; all pending applications were disposed of accordingly.

Source reference: p. 25
Rajasthan High Court

Original Court PDF

HINDUSTAN ZINC LIMITEDvsRAJASTHAN ELECTRICITY REGULATORY COMMISSION

Rajasthan High Court · June 19, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment