Delhi High Court

Statutory Confidentiality Under Section 42A Renders Documents Sourced from Separate Arbitrations Inadmissible in Evidence

Jpc Infrastrucrure And Constructions Private Limited vs Alstom Transport India Limited

Delhi High CourtJUDGMENT: July 06, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The dispute arose from a sub-contract dated 15.12.2015 for civil and electrical works under the Eastern Dedicated Freight Corridor Project.

Source reference: paras. 3-5

The Petitioner alleged that the Respondent failed to provide encumbrance-free site access, causing delays.

Source reference: para. 8

The Respondent eventually terminated the contract due to the Petitioner's alleged non-performance.

Source reference: para. 11

During arbitration, the Petitioner sought to rely on a "Rejected Letter" dated 07.06.2017 sent by the Respondent to a third party (DFCCIL), which allegedly contained admissions regarding site access issues.

Source reference: paras. 15-16

The Arbitral Tribunal, in its award dated 15.11.2023, declined to admit this letter, citing confidentiality under Section 42A of the Arbitration and Conciliation Act, 1996.

Source reference: paras. 18-19

The Petitioner challenged the rejection of four specific claims (Nos. 2, 3, 13, and 16) before the Delhi High Court under Section 34 of the Act.

Source reference: para. 2
02

Issues

1. Whether the Arbitral Tribunal committed a patent illegality or jurisdictional error by excluding the "Rejected Letter" from evidence on the grounds of statutory confidentiality.

Source reference: para. 65

2. Whether the mandates of Section 42A of the Arbitration and Conciliation Act, 1996, apply to documents that may have entered the public domain through other court proceedings.

Source reference: para. 87
03

Law Applied

The court primarily applied Section 42A of the Arbitration and Conciliation Act, 1996, which mandates that the arbitrator and parties maintain the confidentiality of all arbitral proceedings.

Source reference: para. 67

The court relied on the principle that the scope of judicial interference under Section 34 is limited to grounds of "patent illegality" and "fundamental policy of Indian law," as delineated in OPG Power Generation (P) Ltd. v. Enexio Power Cooling Solutions (India) (P) Ltd. and Ssangyong Engg. & Construction Co. Ltd. v. NHAI.

Source reference: para. 59, 71

The court applied the doctrine that an arbitrator is the ultimate master of the quantity and quality of evidence.

Source reference: para. 59, 74
04

Reasoning

The Court reasoned that Section 42A, which includes a non-obstante clause, represents a legislative intent to preserve the integrity of the arbitral process through confidentiality.

Source reference: paras. 68-69

The Court rejected the Petitioner's argument that Section 42A creates a duty without a consequence, holding that allowing a document procured in breach of confidentiality to be used as evidence would render the statutory protection illusory.

Source reference: paras. 70-72

The Court found that the Tribunal exercised its evidentiary discretion reasonably by examining the provenance of the letter and finding that the Petitioner likely obtained it via its counsel who was involved in the Respondent’s separate arbitration with DFCCIL.

Source reference: paras. 64, 73

The Court held that the ICC Rules invoked by the Petitioner could not override the mandatory statutory provisions of the seat of arbitration (India).

Source reference: paras. 82-83

The Court noted that the Tribunal had independent, self-sustaining reasons for rejecting the claims which the Petitioner failed to challenge.

Source reference: para. 91
05

Holding

The Court dismissed the Petition, holding that the Tribunal’s decision to exclude the confidential letter was a possible view and did not constitute patent illegality or a violation of public policy.

The Court affirmed that Section 42A imposes a mandatory obligation that tribunals must respect to prevent the unauthorized use of materials from separate arbitral proceedings.

Source reference: para. 92

The Impugned Award dated 15.11.2023 was upheld in its entirety.

Source reference: para. 96
Delhi High Court

Original Court PDF

Jpc Infrastrucrure And Constructions Private LimitedvsAlstom Transport India Limited

Delhi High Court · July 06, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment