Gujarat High Court

Statutory Interest at 15% is Mandatory on Shortfall of Compensation Beyond One Year From Possession

STATE OF GUJARAT vs LAXMANBHAI GANPATBHAI PATEL

Gujarat High CourtJUDGMENT: July 20, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The respondent-claimants’ lands in Village Detroj, Ahmedabad, were acquired for the Narmada Canal project. An award under Section 11 of the Land Acquisition Act, 1894, was passed on March 19, 1996

Source reference: p. 2

The Reference Court subsequently enhanced the compensation on November 3, 1999

Source reference: p. 2

Although the State deposited a portion of the compensation on July 30, 2003, there remained a shortfall of ₹1,74,384/-

Source reference: p. 3-4

The Executing Court allowed the application, directing the State to pay the principal shortfall plus 15% interest for 6,728 days (the delay period) under Section 28 of the Act

Source reference: p. 2, 12

The State challenged this order, alleging it amounted to "interest upon interest" and was contrary to settled law

Source reference: p. 5
02

Issues

1. Whether the Reference Court erred in granting 15% interest on the delayed payment of the remaining compensation amount for the period between July 31, 2003, and December 31, 2021

Source reference: p. 6, 8

2. Whether the award of interest under Section 28 of the Land Acquisition Act constitutes impermissible "interest upon interest"

Source reference: p. 5
03

Law Applied

The Court primarily applied Section 28 of the Land Acquisition Act, 1894, which mandates interest on excess compensation at 9% p.a. for the first year from taking possession and 15% p.a. thereafter until the excess is paid into Court

Source reference: p. 8

The Court further relied on Section 34 of the Act regarding interest on unpaid compensation

Source reference: p. 8-9

Precedentially, the Court followed Gurpreet Singh v. Union of India (2006) 8 SCC 458 regarding the calculation of interest

Source reference: p. 6

Union of India v. Budh Singh (1995) 6 SCC 233, which established that the Act is a self-contained code and Courts cannot award interest outside the statutory rates and manner prescribed by Sections 28 and 34

Source reference: p. 10-11
04

Reasoning

The Court examined the statutory framework of Sections 28 and 34, noting that these are the exclusive provisions governing the State's liability for interest in land acquisition cases

Source reference: p. 10

Under the proviso to Section 28, once a period of one year has expired from the date of possession, any unpaid excess compensation must attract interest at the statutory rate of 15% p.a. until deposited

Source reference: p. 8, 12

The Court found that the Executing Court did not grant "interest upon interest" but correctly applied the statutory rate to the principal shortfall that remained unpaid for 6,728 days

Source reference: p. 12

Equity has no role in altering these fixed statutory rates

Source reference: p. 11
05

Holding

The High Court dismissed the State's petitions, holding that the Executing Court’s order was just, proper, and in strict compliance with Section 28 of the Land Acquisition Act

The Court affirmed the direction to the State (Petitioner No. 2) to pay the total sum of ₹4,72,066/-, comprising the principal shortfall of ₹1,25,385/- and ₹3,46,681/- as interest at 15% for the delayed period. Rule discharged

Source reference: p. 12-13
Gujarat High Court

Original Court PDF

STATE OF GUJARATvsLAXMANBHAI GANPATBHAI PATEL

Gujarat High Court · July 20, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment