Facts
The petitioner sought a writ of mandamus to restrain the authorities from demolishing a Perumal Temple situated in T.S. No. 18, Block-1, Ward-B, Anbu Nagar, Namakkal, alleging that they were acting without proceedings under the Highways Act.
Source reference: pp. 1–2, paras. 1–2The Highways authority had issued an encroachment-removal notice dated 21 February 2025.
Source reference: pp. 3–4, paras. 5–6Earlier challenges to notices concerning the same site were brought in W.P. Nos. 21157 and 47037 of 2025; the first was withdrawn and the second dismissed.
Source reference: pp. 3–4, paras. 5–6A later mandamus petition by S. Mohan was also withdrawn.
Source reference: pp. 3–4, paras. 5–6After a final notice dated 25 September 2026, the petitioner filed the present petition seeking the same relief.
Source reference: pp. 4–5, para. 7Issues
1. Whether the petitioner was entitled to a mandamus restraining the authorities from removing the temple as an alleged highway encroachment.
Source reference: pp. 1–2, paras. 1–32. Whether the present petition, following earlier proceedings concerning the same site and relief, constituted an abuse of the process of the Court.
Source reference: pp. 3–5, paras. 5–8Law Applied
The Court considered the authorities’ action under the Tamil Nadu Highways Act to remove an encroachment, noting that a notice had been issued under that Act.
Source reference: p. 3, para. 5It also applied the principle that repeated proceedings pursuing substantially the same relief may amount to an abuse of the process of the Court.
Source reference: pp. 4–5, paras. 5–8Reasoning
The Court traced the successive challenges to the proposed removal, including the earlier petitions that were withdrawn or dismissed, and found that the present petitioner sought the same relief after the authorities issued a final notice.
Source reference: pp. 3–5, paras. 5–7It concluded that the successive proceedings, brought by different persons, were attempts to prevent the authorities from acting under the Highways Act and amounted to an abuse of process.
Source reference: p. 5, paras. 7–8It therefore found no merit in the petition.
Source reference: no citationHolding
The Court dismissed the writ petition as an abuse of the process of the Court
and imposed costs of ₹10,000, payable to the Tamil Nadu Advocate’s Clerks’ Association, Madras High Court, within four weeks. The connected interim application was also dismissed.
Source reference: p. 5, para. 8Original Court PDF