Bombay High Court

Supplementary lease deeds granting unlimited time for completion override original construction time-limits in composite projects.

Indian Newspapaer Society vs Mumbai Metropolitan Region Development Authority And Anr

Bombay High CourtJUDGMENT: April 08, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner, a non-profit company, was allotted Plot No. C-63 in Bandra-Kurla Complex (BKC) by the Respondent (MMRDA) on a long-term lease for the construction of an office complex

Source reference: para. 5-6

A Lease Deed was executed on April 9, 2008, which stipulated that construction must be completed within four years (Article 2(d)), failing which additional premium/penalty would be charged for extensions (Article 2(e))

Source reference: para. 9

Initially, the Floor Space Index (FSI) was 2.00, but it was later enhanced to 4.00, leading the Petitioner to acquire additional built-up area (BUA)

Source reference: para. 10, 13

A Supplementary Lease Deed (SLD) was executed on April 22, 2013, which expressly stated in Article 2(c) that there would be "no time limit" for completion of the building using the additional BUA

Source reference: para. 14, 59

Despite this, MMRDA issued demand notices in 2014 and 2017 seeking penalties for the delay in completion beyond the original four-year window

Source reference: para. 24, 28

The Petitioner paid approximately ₹22.63 Crores under protest and filed this Writ Petition challenging the demand notices

Source reference: para. 25-26, 87
02

Issues

1. Whether the Writ Petition is maintainable given the existence of an alternative remedy under Section 44 of the MMRDA Act and the presence of disputed questions of fact.

Source reference: para. 29, 37

2. Whether the demand for penalty/additional premium is contrary to the terms of Article 2(c) of the Supplementary Lease Deed.

Source reference: para. 3, 61

3. Whether the Respondent’s policy of granting a six-year completion period only to leases executed after August 2015 is arbitrary and discriminatory under Article 14 of the Constitution.

Source reference: para. 52, 81
03

Law Applied

The court primarily applied Article 14 of the Constitution of India, which mandates fairness in State action and prohibits arbitrariness

Source reference: para. 40

It relied on the principle of Contra Proferentem, which dictates that any ambiguity in a contract drafted by one party (the State) must be resolved against that party

Source reference: para. 69

The court further applied Section 72 of the Indian Contract Act, 1872, regarding the obligation to refund money paid under coercion or duress

Source reference: para. 73

It followed the precedent in Raghuleela Builders Pvt. Ltd. v. MMRDA, which held that applying time-extension benefits only to post-2015 leases constitutes an arbitrary classification without intelligible differentia

Source reference: para. 46, 81
04

Reasoning

The Court first addressed maintainability, holding that while contractual, the dispute involved the "public law character" of a State instrumentality (MMRDA), and Section 44 of the MMRDA Act did not provide an efficacious remedy for interpreting lease terms

Source reference: para. 37, 42

On the merits, the Court observed that Article 2(c) of the SLD specifically waived the time limit for the "integral" composite construction

Source reference: para. 60-61

The Court reasoned that once the additional BUA was allotted for the same building, segregating the construction into phases with different deadlines was impossible, as facilities like fire systems and elevators are common to the entire structure

Source reference: para. 51, 70

Applying the Contra Proferentem rule, the Court found that any ambiguity between the 2008 and 2013 deeds must be resolved in favor of the Petitioner

Source reference: para. 71

Furthermore, the Court found the Respondent's 2017 demand notice vague and in violation of natural justice, as no specific breach was detailed

Source reference: para. 65

Finally, it held that the Petitioner’s payments were made under "duress and coercion" to save the project from lease determination, triggering the right to a refund under Section 72 of the Contract Act

Source reference: para. 72, 78
05

Holding

The Court allowed the Writ Petition, setting aside the demand notices dated August 22, 2014, and September 12, 2017, as illegal and arbitrary

It held that the "no time limit" clause in the Supplementary Lease Deed displaced the original four-year restriction

Source reference: para. 61

The Court directed MMRDA to refund the total penalty amount of ₹22,63,59,150/- to the Petitioner within 90 days, failing which the amount would carry interest at 14% per annum from the date of the order until realization

Source reference: para. 87
Bombay High Court

Original Court PDF

Indian Newspapaer SocietyvsMumbai Metropolitan Region Development Authority And Anr

Bombay High Court · April 08, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment