Facts
Agra Development Authority invited tenders for internal development works in Township 1 and Township 4.
Source reference: para. 4The petitioner’s name appeared on the Authority’s website as technically qualified, but the Authority subsequently cancelled both tenders on 25 April 2026, stating that the cancellation was due to “unforeseen circumstances,” and issued fresh tenders.
Source reference: para. 4The petitioner alleged that the cancellation was arbitrary and intended to favour other bidders, and challenged both the cancellation and a show-cause notice proposing forfeiture of its earnest money.
Source reference: para. 7The Authority maintained that the petitioner had been wrongly shown as technically qualified despite lacking the required experience in township infrastructure works.
Source reference: para. 10In the fresh tender process, the petitioner did not participate, and letters of intent were issued to respondents 5 and 6.
Source reference: para. 10On examining the original records, the Court found that the petitioner had been assessed as lacking relevant experience, including experience in sewerage and drainage works.
Source reference: para. 25Issues
1. Whether cancellation of the tenders for Township 1 and Township 4 was a colourable exercise of power warranting interference under Article 226.
Source reference: para. 19(I)2. Whether the show-cause notice dated 15 May 2026 was liable to be quashed.
Source reference: para. 19(II)3. Whether the petitioner’s technical bid had been illegally rejected and the petitioner was qualified.
Source reference: para. 19(III)Law Applied
Public authorities conducting procurement must act fairly, transparently, and non-arbitrarily, consistently with Article 14; their tender decisions remain subject to judicial review under Article 226.
Source reference: para. 20A public decision must be supported by reasons, and reasons absent from the impugned order ordinarily cannot be supplied later through an affidavit (*Mohinder Singh Gill v. Chief Election Commissioner*, (1978) 1 SCC 405).
Source reference: para. 22The Court also relied on *Subodh Kumar Singh Rathour v. Chief Executive Officer*, (2024) 15 SCC 461, on the requirement for reasoned State action.
Source reference: para. 22A challenge to a show-cause notice ordinarily succeeds only where mala fides, a predetermined decision, or patent lack of jurisdiction is shown (*J. Sri Nisha v. Special Director, Adjudicating Authority, Directorate of Enforcement*, 2026 INSC 309).
Source reference: para. 30Essential tender eligibility conditions, including relevant work-experience requirements, must be applied and cannot be diluted (*Micky Traders v. L.R.Y. Labour Contractors*, 2026 INSC 1025).
Source reference: para. 20Reasoning
The Court observed that the cancellation order itself gave no explanation beyond “unforeseen circumstances,” and that the tender documents did not identify such circumstances as a basis for cancellation; it therefore found the order deficient in stated reasons and not justified by the tender conditions.
Source reference: para. 21On reviewing the original records, however, the Court found that the petitioner had been recorded as ineligible because its experience did not match the required township-development work and the value requirement, and that its submitted certificate concerned road widening and strengthening rather than sewerage and drainage infrastructure.
Source reference: para. 26The Court treated the petitioner’s erroneous inclusion as technically qualified as having tainted the tender process and found substantial justification for cancellation, concluding that the decision was not discriminatory or mala fide.
Source reference: para. 28As to the show-cause notice, no final order had been made, and the petitioner had not established mala fides, predetermination, or lack of jurisdiction.
Source reference: para. 30Holding
The Court answered all three issues against the petitioner: it found no ground for judicial interference with the tender cancellation, declined to quash the show-cause notice, and held that the petitioner had not established that its technical bid was wrongly rejected.
The writ petition was dismissed, with no order as to costs; the Authority remained free to proceed with the show-cause notice in accordance with law.
Source reference: para. 34Original Court PDF
M/S. Balaji ConstructionvsState Of U.P. And 3 Others
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
