Gauhati High CourtAdministrative and Public LawCivil Procedure and Evidence

The first day is excluded when computing a limitation period for acts to be done "within" a specified time.

M/S Pp Plastic And Industries Pvt Ltdv.The Union Of India And 5 Ors

The first day is excluded when computing a limitation period for acts to be done "within" a specified time.. M/S Pp Plastic And Industries Pvt Ltd vs The Union Of India And 5 Ors. Gauhati High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the application filed by the Petitioner on 29.03.2018 was within the prescribed period of "one year from the date of commencement of commercial production" (29.03.2017) as per Clause (vii) of the Operational Guidelines.

The court held

The Court held that the Petitioner filed the application within the prescribed one-year period

It also directed

The Court set aside the impugned minutes of the meetings dated 06.04.2019, 10.10.2019, and 17.08.2022 that rejected the claim on the grounds of delay

The Respondent Authorities were directed to consider the Petitioner’s claim on its merits, subject to necessary verification, and to complete the exercise within six months. The writ petition was disposed of in favor of the Petitioner

01Facts

The Petitioner, an industrial unit, expanded its operations under the North East Industrial and Investment Promotion Policy, 2007 (NEIIPP) and commenced commercial production on 29.03.2017

pp. 3-4

Under Clause (vii) of the Central Capital Investment Subsidy (CCIS) Scheme Operational Guidelines, claims for subsidy must be filed "within one year from the date of commencement of commercial production"

p. 4

The Petitioner filed its claim on 29.03.2018

p. 5

The Respondent Authorities rejected the claim in multiple meetings held between 2019 and 2022, asserting the application was filed on the 366th day and was therefore time-barred by one day

pp. 5-6

02Issues

i.1. Whether the application filed by the Petitioner on 29.03.2018 was within the prescribed period of "one year from the date of commencement of commercial production" (29.03.2017) as per Clause (vii) of the Operational Guidelines.

p. 6 / para. 10, 13

03Law Applied

The court primarily applied the principle of "exclusion of the first day" in the computation of time as established in Section 9 of the General Clauses Act, 1897

p. 10

It relied on the Supreme Court precedents of Haru Das Gupta v. State of West Bengal, which held that when an act must be done "within" a specified period from a given date, the day on which the cause of action arose is excluded; Saketh India Ltd. v. India Securities Ltd. and Econ Antri Ltd. v. Rom Industries Ltd., which reaffirmed this rule in different statutory contexts; and Tarun Prasad Chatterjee v. Dinanath Sharma, which clarified that the word "from" indicates the opening day must be excluded to avoid prejudice to the claimant

pp. 7-11

Provisions in the judgment · 2 · Linked ones open on LawLens

General Clauses Act, 1897 Section 9

Representation of the People Act, 1951 Section 81

04Reasoning

The Court analyzed the phrase "within one year from the date of commencement of commercial production" found in Clause (vii) of the Guidelines

p. 7

Applying the established rules of construction, the Court determined that because the word "from" was used, the starting date (29.03.2017) must be excluded from the one-year calculation

pp. 11-12

By excluding 29.03.2017, the limitation period began on 30.03.2017 and concluded at the end of 29.03.2018

p. 12

The Court reasoned that this interpretation is necessary to ensure parties receive the full benefit of the allotted time, particularly if the event triggering the period (commencement of production) occurred late in the day

pp. 10-11

Consequently, the Petitioner's filing on 29.03.2018 was found to be on the final day of the permissible window, not one day late

p. 12

05Holding

The Court held that the Petitioner filed the application within the prescribed one-year period

p. 12

The Court set aside the impugned minutes of the meetings dated 06.04.2019, 10.10.2019, and 17.08.2022 that rejected the claim on the grounds of delay

p. 12

The Respondent Authorities were directed to consider the Petitioner’s claim on its merits, subject to necessary verification, and to complete the exercise within six months. The writ petition was disposed of in favor of the Petitioner

p. 13
Gauhati High Court

Original Court PDF

M/S Pp Plastic And Industries Pvt LtdvsThe Union Of India And 5 Ors

Gauhati High Court · May 12, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment