Facts
The petitioner contractor sought payment of ₹4,09,942 for protection works at Balole Nallah, which he said were allotted by the Flood Control Division and completed.
Source reference: para. 3–6, 10The respondents’ communications acknowledged the work and the outstanding amount, but payment remained unpaid.
Source reference: para. 3–6, 10The respondents opposed the writ petition on the grounds that mandatory codal requirements—including Administrative Approval, Technical Sanction and e-tendering—had not been followed, and that funds were unavailable.
Source reference: para. 3–6, 10Issues
Whether the State may deny payment for public works admittedly executed to its satisfaction solely because of non-compliance with internal procedural requirements, including Administrative Approval and Technical Sanction
Source reference: para. 11Whether the petitioner could obtain relief in writ jurisdiction where the respondents acknowledged the liability but disputed payment on contractual and procedural grounds
Source reference: paras. 5, 12Law Applied
The Court relied on ABL International Ltd. v. ECGC, (2004) 3 SCC 553, and Surya Constructions v. State of U.P., (2019) 16 SCC 794, for the proposition that writ jurisdiction may be exercised to enforce public-law obligations arising from contracts where material facts are undisputed and liability is admitted; arbitrary non-payment of admitted dues may violate Article 14.
Source reference: para. 12It applied the presumption that official acts have been regularly performed (omnia praesumuntur rite et solemniter esse acta) and referred to its decisions in M/S Rightway Constructions Company v. UT of J&K, M/S Krishna Engineering Works v. Jal Shakti Department, and Bilal Ahmad Mir v. UT of J&K concerning payment for work executed under official orders despite alleged internal approval deficiencies.
Source reference: para. 13It also relied on Section 70 of the Indian Contract Act, 1872, as explained in State of West Bengal v. B.K. Mondal & Sons, AIR 1962 SC 779: a person who lawfully performs work for another, whose benefit is enjoyed, is entitled to compensation.
Source reference: para. 14Reasoning
The Court found that the respondents’ records acknowledged the allotment and execution of the work, the preparation of bills, and the outstanding liability.
Source reference: paras. 10, 12–16Since the objection concerned departmental procedures that were within the responsibility of departmental officials, the Court held that those alleged lapses could not be used to defeat the contractor’s claim after the work had been executed and its benefit retained.
Source reference: paras. 10, 12–16Given the admitted liability and the absence of a dispute over execution, the Court rejected the maintainability objection and found a legal obligation to process and pay the claim.
Source reference: paras. 10, 12–16Holding
The Court allowed the petition and issued mandamus directing the respondents to verify, process and release the admitted liability of ₹4,09,942 within eight weeks of receiving a certified copy of the judgment.
The petition and connected applications were disposed of accordingly.
Source reference: paras. 17–18Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Indian Contract Act, 18721
Original Court PDF
M/S GUCCHU RAM TH GUCCHU RAMvsUT OF J AND K TH COMMISSIONER SECRETARY IRRIGATION AND FLOOD CONTROL JAMMU AND OTHERS
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
