NCLAT

### Time Extension for Settlement Performance Permissible to Achieve IBC Objective of Corporate Debtor Rehabilitation

Harvinder Singh Sikka v. Nobal Buildtech Pvt. Ltd. Through the Interim Resolution Professional & Ors. [Company Appeal (AT) (Insolvency) No. 256, 287 & 288 of 2026]

NCLATJUDGMENT: no citation3 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Corporate Debtor (CD), Nobal Buildtech Pvt. Ltd., stood as a corporate guarantor for Non-Convertible Debentures issued by Kindle Infraheights Pvt. Ltd. to Respondent No. 3.

Source reference: para. 3(i)-(ii)

Following a default, the Financial Creditor (FC), Orbis Trusteeship Services Pvt. Ltd., initiated Section 7 CIRP proceedings.

Source reference: para. 3(iii)

On 09.05.2025, the parties entered a Settlement Agreement for ₹210 crore, leading to the withdrawal of the CIRP under Section 12A on 31.07.2025.

Source reference: para. 3(vi)-(viii)

The CD paid ₹120 crore but defaulted on a ₹25 crore tranche, leading the FC to file for revival of CIRP via RA 83/2025.

Source reference: para. 3(ix)-(x)

Although the ₹25 crore was subsequently paid and accepted, the Adjudicating Authority (NCLT) restored the CIRP on 07.01.2026, granting only 10 days to pay the remaining ₹90 crore.

Source reference: para. 3(xi)-(xiii)

The NCLT later extended this stay only until 04.02.2026 via order dated 21.01.2026 in IA 312/2026.

Source reference: para. 3(xvi)

The CD appealed, citing delays in fund infusion due to the unavailability of original title deeds.

Source reference: para. 3(xii), 19
02

Issues

Whether the Adjudicating Authority erred in reviving the CIRP and refusing a reasonable extension to pay the balance settlement amount despite substantial part-performance.

Source reference: para. 5, 27

Whether the objectives of the IBC allow for the continuation of CIRP when a bona fide settlement is achievable and the CD is making active efforts to liquidating the debt.

Source reference: para. 25, 28
03

Law Applied

The court primarily applied Section 12A of the Insolvency and Bankruptcy Code (IBC) regarding the withdrawal of CIRP applications.

Source reference: para. 3(vii)

It relied on the principle from *Swiss Ribbons Pvt. Ltd. v. Union of India*, which established that the primary focus of the IBC is the revival and continuation of the CD, rather than being a mere recovery legislation.

Source reference: para. 22-23

The court further cited *Anuj Jain v. Axis Bank Ltd.* regarding the "parental and nursing role" of financial creditors in restructuring loans.

Source reference: para. 24

And *E.S. Krishnamurthy v. Bharat Hi-Tecch Builders Pvt. Ltd.*, which held that settlements must be encouraged to facilitate the rehabilitation of the CD.

Source reference: para. 25

Finally, it exercised inherent powers under Rule 11 of the NCLT Rules, 2016, to grant equitable relief.

Source reference: para. 17
04

Reasoning

The court found that out of a ₹210 crore settlement, a significant sum of ₹120 crore had already been paid to and accepted by the FC.

Source reference: para. 16, 26

It noted that the delay in paying the final ₹90 crore was not due to willful default but was linked to the unavailability of original title deeds (which were in the FC's or Noida Authority's possession), hindering the CD’s ability to complete investor due diligence for fund infusion.

Source reference: para. 7, 19-20

The court reasoned that since the FC is the sole creditor and the CD has demonstrated bona fides by paying more than half the settlement amount, the NCLT’s refusal to grant a 90-day extension was contrary to the IBC’s objective of rehabilitation.

Source reference: para. 27-28

The court underscored that the "pivotal role" of a financial creditor includes facilitating restructuring rather than forcing a "hostile takeover" through rigid triggers when a viable settlement is in sight.

Source reference: para. 22-25
05

Holding

The Appellate Tribunal allowed IA 312/2026 and modified the NCLT's order dated 21.01.2026.

The court held that the CD is entitled to a 90-day extension from the date of the judgment to pay the balance ₹90 crore.

Source reference: para. 29, 30(ii)

It directed that if the payment is made within this period, the CIRP shall stand terminated and the withdrawal order dated 31.07.2025 shall become operative.

Source reference: para. 30(ii)

The RP and FC were directed to render all necessary assistance to implement the Settlement Deed.

Source reference: para. 30(iii)
NCLAT

Original Court PDF

Harvinder Singh Sikka v. Nobal Buildtech Pvt. Ltd. Through the Interim Resolution Professional & Ors. [Company Appeal (AT) (Insolvency) No. 256, 287 & 288 of 2026]

NCLAT · no citation

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment