Facts
The Petitioner, a sole proprietorship, participated in a tender invited by the Respondent (NTPC) for the procurement of biomass pellets via the GeM Portal
Source reference: para 1-2Clause 6(C) of the Invitation for Bids (IFB) required bidders to submit technical experience documents duly certified by an "Independent Statutory Auditor of their Company" or a "specified Third-Party Inspection Agency (TPIA)"
Source reference: para 3The Petitioner initially submitted documents certified by its Chartered Accountant
Source reference: para 4On March 20, 2026, the Respondent requested specific TPIA-verified documents by a deadline of March 24, 2026
Source reference: para 5The Petitioner first provided certification from "Madre Certification Pvt. Ltd," which was not an empaneled/specified TPIA
Source reference: para 6Although the Petitioner eventually obtained a certificate from an approved agency ("BSCIC Certifications") on March 24, it failed to submit or upload it within the prescribed time due to alleged portal issues, eventually submitting it physically on March 27
Source reference: para 6, 12-13Consequently, the Respondent disqualified the Petitioner for failing to meet technical requirements within the stipulated timeframe
Source reference: para 7Issues
1. Whether the disqualification of the Petitioner for failure to submit specified TPIA certification within the prescribed deadline was arbitrary or unlawful
Source reference: para 9, 192. Whether the court should exercise judicial review to waive a procedural technicality in a commercial tender
Source reference: para 14, 18Law Applied
The court primarily applied the principles of judicial review in administrative action as established in Jagdish Mandal v. State of Orissa, which mandates that courts must exercise restraint in tender matters unless the decision is vitiated by mala fides, arbitrariness, or irrationality
Source reference: para 18It applied the principle that a contract is a commercial function where "principles of equity and natural justice stay at a distance"
Source reference: para 18The court further relied on the doctrine that tender timelines and cut-off dates are sacrosanct to ensure equal treatment of bidders
Source reference: para 21Additionally, the court noted that a bidder who participates in a process without challenging the terms (Clause 6(C)) is precluded from challenging those terms after being disqualified
Source reference: para 25Reasoning
The Court observed that Clause 6(C) was an essential condition of the IFB and clearly mandated certification by either a statutory auditor (for companies) or a specified TPIA
Source reference: para 20Since the Petitioner was a sole proprietorship, the requirement for a specified TPIA was mandatory
Source reference: para 20, 24The Court found that the Petitioner’s failure to submit the correct certification by the deadline of March 24, 2026, was a fatal lapse, as subsequent attempts to cure deficiencies cannot be entertained without compromising the integrity of the bidding process
Source reference: para 21It rejected the Petitioner’s claim of ambiguity in the clause, noting that the IFB provided a list of specified agencies
Source reference: para 20Furthermore, the Court held that while the Respondent had discretionary power under Clause 25.2 to waive minor irregularities, it was not legally bound to do so; refusing to relax mandatory timelines for one bidder does not constitute arbitrariness
Source reference: para 28-30Holding
The Court answered that it cannot direct the Respondent to accept documents beyond a prescribed deadline, as doing so would rewrite the tender terms and create an unfair advantage
The Court dismissed the petition, holding that the Respondent’s decision to disqualify the Petitioner was lawful and strictly in accordance with the tender terms
Source reference: para 22, 33No mala fides or irrationality was found in the decision-making process
Source reference: para 31The challenge to the validity of the conditions was rejected as the Petitioner had already participated in the process
Source reference: para 25All pending applications were disposed of
Source reference: para 33Original Court PDF
Navya IndustriesvsNtpc Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in