Delhi High Court
Arbitration and MediationCivil Procedure and Evidence

Under Section 11, the court’s inquiry is confined to prima facie existence of an arbitration agreement.

Zillion Infraprojects Pvt. Ltd vs Ntpc Bhel Power Projects Pvt Ltd

Delhi High CourtJUDGMENT: September 29, 20262 MIN READSOURCE JUDGMENT
Under Section 11, the court’s inquiry is confined to prima facie existence of an arbitration agreement.. Zillion Infraprojects Pvt. Ltd vs Ntpc Bhel Power Projects Pvt Ltd. Delhi High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The parties’ Work Order dated 12 February 2015 and Contract Agreement dated 10 July 2015 concerned the erection and commissioning package for the Feroz Gandhi Unchahar Thermal Power Project.

Source reference: p. 1–3, paras. 1–2

Clause 29 of the Work Order, read with Clause 24 of the General Conditions of Contract, provided for arbitration, with the arbitrator to be appointed by NBPPL’s General Manager.

Source reference: p. 1–3, paras. 1–2

After disputes arose, the petitioner invoked arbitration by notice dated 22 June 2026 under Section 21 of the Arbitration and Conciliation Act, 1996.

Source reference: p. 3, paras. 3–4

The respondent did not appear despite service.

Source reference: p. 3, paras. 3–4

The petitioner sought appointment of an independent sole arbitrator under Section 11(6).

Source reference: p. 1, para. 1
02

Issues

Whether the Court should appoint a sole arbitrator under Section 11(6) where the arbitration agreement’s existence was undisputed.

Source reference: p. 3–4, paras. 5–7

Whether the disputes’ arbitrability or jurisdictional objections should be determined at the Section 11 stage or left to the arbitrator.

Source reference: p. 4, para. 11
03

Law Applied

Section 11 of the Arbitration and Conciliation Act, 1996 limits the Court’s inquiry at the appointment stage to examining the prima facie existence of an arbitration agreement, as stated in SBI General Insurance Co. Ltd. v. Krish Spinning, 2024 SCC OnLine SC 1754.

Source reference: p. 3, para. 5

Section 21 governs commencement of arbitral proceedings upon receipt of a request to refer the dispute to arbitration.

Source reference: p. 3, para. 3

Section 12(2) requires the appointed arbitrator to make the requisite disclosure.

Source reference: p. 4, para. 9

Under the parties’ arbitration clause, disputes were referable to arbitration under the 1996 Act, with Delhi as the venue.

Source reference: p. 2–3, paras. 2, clauses 29.4 and 29.9
04

Reasoning

The Court found that the contract contained a valid arbitration clause and that the petitioner had invoked it by notice; the respondent’s non-appearance did not displace the prima facie basis for appointment.

Source reference: p. 3–4, paras. 3–7

Applying the limited Section 11 inquiry, the Court appointed a sole arbitrator.

Source reference: p. 4, paras. 8, 11–12

It left questions of arbitrability and jurisdiction for the arbitrator to decide, and clarified that its observations were not to influence the arbitration’s merits.

Source reference: p. 4, paras. 8, 11–12
05

Holding

The petition was allowed in terms of appointing Mr. Manu Beri, Advocate, as sole arbitrator.

He was directed to enter upon the reference within two weeks and furnish the disclosure required by Section 12(2); the arbitration is to proceed under the rules and aegis of the Delhi International Arbitration Centre, with fees as per its schedule.

Source reference: p. 4, paras. 8–10

The petition and pending application(s) were disposed of.

Source reference: p. 5, para. 14
06

Acts & Sections Cited

3 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19963

Delhi High Court

Original Court PDF

Zillion Infraprojects Pvt. LtdvsNtpc Bhel Power Projects Pvt Ltd

Delhi High Court · September 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment