Facts
The parties’ Work Order dated 12 February 2015 and Contract Agreement dated 10 July 2015 concerned the erection and commissioning package for the Feroz Gandhi Unchahar Thermal Power Project.
Source reference: p. 1–3, paras. 1–2Clause 29 of the Work Order, read with Clause 24 of the General Conditions of Contract, provided for arbitration, with the arbitrator to be appointed by NBPPL’s General Manager.
Source reference: p. 1–3, paras. 1–2After disputes arose, the petitioner invoked arbitration by notice dated 22 June 2026 under Section 21 of the Arbitration and Conciliation Act, 1996.
Source reference: p. 3, paras. 3–4The respondent did not appear despite service.
Source reference: p. 3, paras. 3–4The petitioner sought appointment of an independent sole arbitrator under Section 11(6).
Source reference: p. 1, para. 1Issues
Whether the Court should appoint a sole arbitrator under Section 11(6) where the arbitration agreement’s existence was undisputed.
Source reference: p. 3–4, paras. 5–7Whether the disputes’ arbitrability or jurisdictional objections should be determined at the Section 11 stage or left to the arbitrator.
Source reference: p. 4, para. 11Law Applied
Section 11 of the Arbitration and Conciliation Act, 1996 limits the Court’s inquiry at the appointment stage to examining the prima facie existence of an arbitration agreement, as stated in SBI General Insurance Co. Ltd. v. Krish Spinning, 2024 SCC OnLine SC 1754.
Source reference: p. 3, para. 5Section 21 governs commencement of arbitral proceedings upon receipt of a request to refer the dispute to arbitration.
Source reference: p. 3, para. 3Section 12(2) requires the appointed arbitrator to make the requisite disclosure.
Source reference: p. 4, para. 9Under the parties’ arbitration clause, disputes were referable to arbitration under the 1996 Act, with Delhi as the venue.
Source reference: p. 2–3, paras. 2, clauses 29.4 and 29.9Reasoning
The Court found that the contract contained a valid arbitration clause and that the petitioner had invoked it by notice; the respondent’s non-appearance did not displace the prima facie basis for appointment.
Source reference: p. 3–4, paras. 3–7Applying the limited Section 11 inquiry, the Court appointed a sole arbitrator.
Source reference: p. 4, paras. 8, 11–12It left questions of arbitrability and jurisdiction for the arbitrator to decide, and clarified that its observations were not to influence the arbitration’s merits.
Source reference: p. 4, paras. 8, 11–12Holding
The petition was allowed in terms of appointing Mr. Manu Beri, Advocate, as sole arbitrator.
He was directed to enter upon the reference within two weeks and furnish the disclosure required by Section 12(2); the arbitration is to proceed under the rules and aegis of the Delhi International Arbitration Centre, with fees as per its schedule.
Source reference: p. 4, paras. 8–10The petition and pending application(s) were disposed of.
Source reference: p. 5, para. 14Acts & Sections Cited
3 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19963
Original Court PDF
Zillion Infraprojects Pvt. LtdvsNtpc Bhel Power Projects Pvt Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
