Facts
The Petitioners imported duty-free raw materials under Advance Authorisation Licences issued by the DGFT and were required to manufacture and export finished goods within the prescribed Export Obligation Period.
Source reference: para. 2–6Customs alleged that the Petitioners diverted the imported materials into the domestic market through purported job-work arrangements, without fulfilling the export obligation, in breach of the actual-user condition under Notification No. 18/2015-Cus.
Source reference: para. 2–6A Show Cause Notice dated 24 June 2022 was issued under Sections 28(4) and 28AAA of the Customs Act, 1962, proposing recovery of approximately ₹20.18 crore in differential customs duty, along with interest.
Source reference: para. 6The Petitioners had earlier approached the High Court seeking extension of the Export Obligation Period and permission to procure copper from the domestic market. The High Court dismissed the proceedings on 8 December 2023 after the DGFT rejected their representations.
Source reference: para. 7–11During the adjudication of the SCN, an eight-month extension was granted under the first proviso to Section 28(9), and the proceedings were subsequently transferred to the Call Book after the Petitioners themselves sought deferment pending the earlier writ petition and relied upon the interim order restraining coercive action.
Source reference: para. 12, 29–30After dismissal of the earlier writ petition, the proceedings were revived and culminated in an Order-in-Original dated 29 November 2024 confirming the duty demand, with interest under Sections 28(4), 28AA and 28AAA.
Source reference: para. 13Issues
Whether the Order-in-Original dated 29 November 2024 was passed beyond the statutory period prescribed under Sections 28(9) and 28(9A) of the Customs Act, 1962, thereby rendering the proceedings without jurisdiction?
Source reference: para. 19–20, 29–42Whether the pendency of the earlier writ petition and the interim order restraining coercive action constituted a circumstance under Section 28(9A)(b), so that limitation would run only from the cessation of that circumstance?
Source reference: para. 30–35Whether the absence of a separate formal communication regarding the Call Book transfer or the reasons for non-determination invalidated the operation of Section 28(9A)?
Source reference: para. 31–40Whether the Petitioners were entitled to writ relief despite the availability of an efficacious statutory appellate remedy and their conduct during the adjudication proceedings?
Source reference: para. 43–48Law Applied
The Court applied Section 28(9)(b) of the Customs Act, 1962, which requires determination of duty or interest within one year from the date of notice in cases falling under Section 28(4), subject to the statutory extension under the first proviso; the second proviso provides that proceedings are deemed concluded if determination is not made within the permissible period.
Source reference: para. 18Section 28(9A) operates notwithstanding Section 28(9) where determination is prevented by specified circumstances, including a pending appeal or interim order of the Appellate Tribunal, High Court or Supreme Court; in such cases, the statutory period begins when the relevant circumstance ceases to exist, subject to informing the person concerned of the reason for non-determination.
Source reference: para. 18The Court distinguished Vos Technologies Pvt. Ltd. v. Principal Additional Director General, 2024 SCC OnLine Del 8756, because it concerned pre-2018 SCNs and prolonged, unexplained Call Book pendency under the unamended statutory regime.
Source reference: para. 23–28The Court also applied the principles that writ jurisdiction under Article 226 is discretionary and ordinarily will not be exercised where an efficacious alternative remedy exists, and that a party cannot approbate and reprobate by relying on a circumstance to defer adjudication and later relying on the resulting delay to seek equitable relief.
Source reference: para. 43–47The Court considered, but did not find applicable, the Supreme Court’s interim direction in Union of India v. GMR Airport Infrastructure Ltd., SLP(C) No. 5392/2025.
Source reference: para. 21–28Reasoning
The SCN was issued under Section 28(4); therefore, the ordinary period under Section 28(9)(b) was one year from 24 June 2022, subject to extension.
Source reference: para. 29However, the Petitioners themselves sought deferment of adjudication on the basis of the pending writ petition and the interim order restraining coercive recovery, and expressly reserved the right to file a substantive reply after disposal of that petition.
Source reference: para. 30The Court held that this situation fell within Section 28(9A)(b), since the interim order and the issues pending in the earlier writ petition were directly relevant to the Petitioners’ liability under the Advance Authorisations.
Source reference: para. 33–35The Call Book transfer was treated only as an administrative consequence of the statutory circumstance; it was not itself the source of the limitation exclusion.
Source reference: para. 35–36Although Section 28(9A) ordinarily requires the proper officer to inform the noticee of the reason for non-determination, that requirement was substantially satisfied because the Petitioners themselves had identified and relied upon the very circumstance preventing adjudication.
Source reference: para. 37–40The relevant circumstance ceased when the earlier writ petition was dismissed on 8 December 2023. The statutory period consequently commenced from that date, and the OIO dated 29 November 2024 was passed within the applicable one-year period.
Source reference: para. 41–42Independently, the Court declined to exercise writ jurisdiction because the Petitioners had an efficacious statutory appeal and had not challenged the substantive findings regarding diversion of goods and non-fulfilment of export obligations.
Source reference: para. 43–47Their failure to inform the adjudicating authority of the dismissal of the earlier writ petition, after having sought deferment on its pendency, further disentitled them to equitable relief.
Source reference: para. 43–47Holding
The Court held that the OIO dated 29 November 2024 was not barred by limitation.
The pendency of the earlier writ petition and the interim order constituted a circumstance under Section 28(9A)(b), and the limitation period began only upon cessation of that circumstance on 8 December 2023.
Source reference: para. 41–42The challenge to the SCN and OIO was therefore rejected.
Source reference: para. 41–42, 48The writ petition and pending application were dismissed, while the Petitioners were granted liberty to pursue the statutory appellate remedy and raise all available grounds before the competent appellate authority; the Court clarified that its observations would not prejudice consideration of those contentions on merits.
Source reference: para. 49–51Acts & Sections Cited
2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Customs Act,19622
Original Court PDF
Gkem International Pvt Ltd & Ors.vsCommissioner Of Customs Icd Ppg And Other Icds
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
