Facts
Lotus Landmarks (India) Pvt. Ltd. (“Lotus”), a land developer, entered into a Joint Venture Agreement dated 17 April 2016 with the landowners for development of the “RVP City” layout at Belagavi.
Source reference: paras. 3–4The agreement contemplated sharing of developed residential plots, completion of the project within 24 months with a six-month grace period, and a specific arbitration procedure under Clause 25 whereby each party was to nominate one arbitrator and the two arbitrators were to appoint an umpire.
Source reference: paras. 15–16Following disputes concerning the development work, the landowners issued notice dated 9 January 2018 and nominated their arbitrator. Lotus did not nominate its arbitrator within the stipulated period.
Source reference: paras. 5–6The landowners’ nominee thereafter proceeded as the sole arbitrator and passed an award dated 28 January 2019 directing Lotus to pay ₹2,21,58,000 with 18% interest, ₹25,00,000 as compensation with 18% interest, and comply with several consequential directions, including termination of the Joint Venture Agreement and power of attorney.
Source reference: paras. 5–6Lotus challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The Principal District Judge, Belagavi dismissed the challenge on 22 April 2022, holding, inter alia, that Lotus had failed to appoint its arbitrator within 30 days, had participated in the proceedings, and had waived its objection to the sole arbitrator.
Source reference: paras. 7–9Lotus filed the present appeal under Section 37(1)(b), principally contending that the arbitral tribunal had not been constituted in accordance with Clause 25.
Source reference: para. 10Issues
1. Whether the arbitral proceedings conducted by the respondent’s nominee as the sole arbitrator, despite Clause 25 requiring each party to nominate an arbitrator and the nominees to appoint an umpire, were vitiated for non-compliance with the agreed procedure?
Source reference: para. 142. Whether the failure of Lotus to nominate its arbitrator within 30 days authorised the landowners’ nominee to proceed as the sole arbitrator without recourse to Section 11(6) of the Arbitration Act?
Source reference: paras. 19–21, 313. Whether Lotus had waived its objection under Section 4 of the Arbitration Act by participating in the arbitral proceedings?
Source reference: paras. 50–57Law Applied
The Court applied Section 34(2)(a)(v) of the Arbitration and Conciliation Act, 1996, under which an award may be set aside where the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the parties’ agreement.
Source reference: para. 44Section 18 requires equal treatment of parties and a full opportunity to present their cases; the principle of equal treatment extends to equal participation in constituting the tribunal.
Source reference: paras. 23–25Under Section 11(6), where a party fails to act under an agreed appointment procedure, the other party must seek the Court’s assistance for appointment rather than unilaterally assume the defaulting party’s role.
Source reference: paras. 31–33Relying on Datar Switchgears Ltd. v. Tata Finance Ltd., (2000) 8 SCC 151, and Deep Trading Co. v. Indian Oil Corporation, (2013) 4 SCC 35, the Court held that non-appointment within 30 days does not, by itself, authorise unilateral appointment or automatically extinguish the agreed appointment mechanism.
Source reference: para. 22Dharma Prathishthanam v. Madhok Construction (P) Ltd., (2005) 9 SCC 686, established that parties must adhere to the agreed appointment procedure and that unilateral appointment and reference are illegal unless validly waived.
Source reference: para. 34The Court also relied on Bhadra International (India) Pvt. Ltd. v. Airports Authority of India, 2026 SCC OnLine SC 7, for the propositions that equal participation in tribunal constitution is part of fairness and party autonomy, and that an award rendered by an incompetent or ineligible tribunal is non-est.
Source reference: paras. 24, 40, 46Section 4 permits waiver only where a party proceeds without objecting within a reasonable time; timely objection prevents waiver.
Source reference: paras. 50–54Reasoning
Clause 25 granted both parties an equal contractual right to nominate an arbitrator, with the two nominees thereafter empowered to appoint an umpire.
Source reference: paras. 15–16Although Lotus failed initially to nominate its arbitrator, that default did not permit the landowners’ nominee to convert himself into the sole arbitrator. The proper course was to invoke Section 11(6) and seek appointment of Lotus’s nominee through the Court.
Source reference: paras. 19–21, 30–33The unilateral assumption of jurisdiction disregarded the agreed tribunal-composition procedure and violated the principles of party autonomy, equal treatment, and fairness under Section 18.
Source reference: paras. 26, 35–39The Court further found that Lotus had not waived its objection: its communications dated 8 March, 12 April, 3 May and 8 May 2018, and its later communication dated 4 January 2019, consistently disputed the sole arbitrator’s authority and sought time or judicial intervention to appoint its nominee.
Source reference: paras. 27–30, 41–43, 51–56The District Court therefore erred in treating Lotus’s limited participation and submission of documents as consent or waiver.
Source reference: paras. 51–56Since the tribunal suffered from a foundational and jurisdictional defect, the entire arbitral proceeding was a nullity, making it unnecessary to examine the other challenges to the award.
Source reference: paras. 38–40, 57–60Holding
The Court answered the principal issue in the affirmative and held that the arbitral tribunal was invalidly constituted because the procedure under Clause 25 was not followed.
The landowners’ nominee could not act as sole arbitrator merely because Lotus had not appointed its nominee; recourse to Section 11(6) was necessary.
Source reference: paras. 58, 60–61Lotus had also not waived its objection under Section 4 because it objected at the earliest stage and repeatedly thereafter.
Source reference: paras. 51–57Accordingly, the order dated 22 April 2022 in Arbitration Petition No. 2 of 2021 and the arbitral award dated 28 January 2019 were set aside.
Source reference: para. 62The respondents were granted liberty to initiate appropriate proceedings afresh under the Joint Venture Agreement, as permissible in law.
Source reference: para. 62Acts & Sections Cited
12 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 1996
Original Court PDF
LOTUS LANDMARKS (INDIA) PVT. LTDvsRVP CITY OWNERS
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
