Facts
The Principal Judge, Family Court, Kasganj, allowed an application under Section 125 Cr.P.C. on 17 September 2024, directing the revisionist to pay maintenance of ₹3,000 per month to the opposite party and ₹1,000 per month each to two minor children, from the date of the application.
Source reference: p.1The revisionist challenged that order by filing a criminal revision with a delay-condonation application, 645 days after the order.
Source reference: p.1, paras. 2–3He argued that the maintenance amount was beyond his means and that the delay was explained in his supporting affidavit.
Source reference: p.1, paras. 2–3When asked whether execution proceedings had been initiated, counsel could not say; no document concerning execution was attached to the paper book.
Source reference: p.2, paras. 4–5Issues
Whether the revisionist showed sufficient grounds to condone the 645-day delay in filing the criminal revision
Source reference: p.3, para. 8Whether the Court should issue or reiterate directions for timely disposal of execution applications in maintenance cases, in light of the Supreme Court’s directions
Source reference: pp. 2–3, paras. 5–7Law Applied
A delay-condonation application may be allowed where the reasons advanced adequately explain the delay; here, the Court assessed the supporting affidavit and found the explanation insufficient.
Source reference: p.3, para. 8Under Section 125 Cr.P.C., the Family Court had ordered maintenance; Sections 125(3) and 128 Cr.P.C. were mentioned in connection with possible execution proceedings, but the Court did not decide any question concerning their application.
Source reference: p.2, paras. 2, 4In Periyammal (Dead) v. V. Rajamani, (2025) 9 SCC 568, the Supreme Court reiterated the direction that execution proceedings be completed within six months and directed High Courts to ensure compliance through their respective district judiciaries.
Source reference: p.2, para. 5The Allahabad High Court’s Registrar General had circulated that direction to courts in Uttar Pradesh by Circular No. 16/Admin G-II dated 24 May 2025.
Source reference: p.2, para. 6Reasoning
The Court found that the revision had been filed 645 days after the maintenance order and that the affidavit did not sufficiently explain the delay.
Source reference: pp. 1, 3, paras. 3, 8The asserted challenge to the amount of maintenance did not overcome that deficiency, so the Court declined to condone the delay.
Source reference: pp. 1, 3, paras. 3, 8Separately, because counsel could not confirm whether execution had been initiated and the record contained no related documents, the Court reiterated the Supreme Court’s six-month disposal direction and directed trial courts in Uttar Pradesh to comply in maintenance cases.
Source reference: pp. 2–3, paras. 4–7Holding
The Court dismissed the delay-condonation application and consequently dismissed the criminal revision as time-barred.
It directed trial courts in Uttar Pradesh to ensure that execution applications in maintenance cases are decided within six months, and directed the Registrar (Compliance) to communicate the order to the Principal Judge, Family Court, Kasganj, for necessary action.
Source reference: p.3, paras. 7, 9Acts & Sections Cited
2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.