01Facts
S. Kumar’s Associates, a sole proprietorship concern, was awarded a contract by South Eastern Coalfields Limited (SECL) for excavation, transportation and allied overburden-removal work at Gare Palma IV/2&3 OCP, Raigarh Area.
¶ 2–3The parties executed an agreement dated 23 December 2018 containing a two-stage in-house dispute-resolution mechanism under Clause 13 and an arbitration clause under Clause 13A.
¶ 2–3After extensions of time, the applicant completed the work on 20 March 2020, and SECL issued a Completion Certificate on 24 April 2020.
¶ 3The applicant alleged that SECL failed to settle the final bill and refund the security amounts, and subsequently imposed penalties and recoveries totalling Rs. 58,71,418.81, including deductions towards diesel de-escalation and other alleged dues.
¶ 4The applicant invoked the first and second stages of the contractual dispute-resolution mechanism by notices dated 16 July 2025 and 29 October 2025, but the disputes remained unresolved.
¶ 5Thereafter, the applicant invoked arbitration under Section 21 of the Arbitration and Conciliation Act, 1996, by notice dated 2 March 2026 and nominated a former High Court Judge as sole arbitrator.
¶ 6SECL neither accepted the nomination nor proposed an alternative arbitrator.
¶ 602Issues
i.Whether the applicant had established the existence of an arbitration agreement and fulfilled the contractual pre-arbitration requirements so as to invoke the jurisdiction of the Court under Section 11(6) of the Arbitration and Conciliation Act, 1996.
¶ 1–2, 5–6ii.Whether, in view of the respondents’ failure to concur in the applicant’s nomination and the parties’ subsequent consensus, a sole arbitrator should be appointed by the Court.
¶ 6–10iii.Whether the merits of the applicant’s monetary claims and SECL’s recoveries required adjudication at the Section 11 stage.
¶ 603Law Applied
Section 7 of the Arbitration and Conciliation Act, 1996 requires an arbitration agreement in writing; Clause 13A of the agreement constituted such an arbitration agreement.
¶ 2Section 21 governs commencement of arbitral proceedings upon receipt of a request for reference to arbitration.
¶ 6Section 11(6) empowers the Court to appoint an arbitrator where the agreed appointment procedure has failed, including where a party fails to act as required under that procedure.
¶ 1 and 6The contractual mechanism under Clauses 13 and 13A required exhaustion of the in-house dispute-resolution process before arbitration could be invoked.
¶ 2 and 5At the appointment stage, the Court was concerned with constituting the arbitral tribunal and did not adjudicate the merits of the parties’ claims, recoveries or counterclaims.
¶ 6Provisions in the judgment · 4 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 7Section 9Section 11Section 21
04Reasoning
The Court found that the agreement contained a valid arbitration clause and that the applicant had invoked and exhausted both stages of the contractual in-house mechanism.
¶ 2 and 5The applicant thereafter issued a valid notice under Section 21 and called upon SECL to concur in the appointment of an arbitrator.
¶ 6SECL failed to respond or nominate an alternative, thereby giving rise to the occasion for action under Section 11(6).
¶ 6The subsequent “Speaking Order” issued by SECL did not extinguish the disputes because it was issued by an officer of a party to the dispute and merely confirmed SECL’s own position; the underlying claims and recoveries remained matters for arbitral adjudication.
¶ 6Since both parties ultimately agreed that a retired District Judge could act as arbitrator and specifically proposed Mr. Ashok Kumar Panda, the Court accepted that consensus and appointed him as sole arbitrator.
¶ 7–1005Holding
The arbitration request was allowed under Section 11(6) of the Arbitration and Conciliation Act, 1996.
¶ 10Mr. Ashok Kumar Panda, retired District Judge, was appointed as the sole arbitrator to adjudicate the disputes between the parties.
¶ 10The Registry was directed to communicate the order to the arbitrator, and his remuneration was to be settled by mutual consent of the parties.
¶ 11–12The Court did not decide the merits of the applicant’s monetary claims or SECL’s alleged recoveries, leaving those issues for determination by the arbitral tribunal.
¶ 6Original Court PDF
S Kumars AssociatesvsSouth Eastern Coalfields Limited SECL
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
