Facts
S. Kumar’s Associates, a sole proprietorship concern, was awarded a contract by South Eastern Coalfields Limited (SECL) for excavation, transportation and allied overburden-removal work at Gare Palma IV/2&3 OCP, Raigarh Area.
Source reference: paras. 2–3The parties executed an agreement dated 23 December 2018 containing a two-stage in-house dispute-resolution mechanism under Clause 13 and an arbitration clause under Clause 13A.
Source reference: paras. 2–3After extensions of time, the applicant completed the work on 20 March 2020, and SECL issued a Completion Certificate on 24 April 2020.
Source reference: para. 3The applicant alleged that SECL failed to settle the final bill and refund the security amounts, and subsequently imposed penalties and recoveries totalling Rs. 58,71,418.81, including deductions towards diesel de-escalation and other alleged dues.
Source reference: para. 4The applicant invoked the first and second stages of the contractual dispute-resolution mechanism by notices dated 16 July 2025 and 29 October 2025, but the disputes remained unresolved.
Source reference: para. 5Thereafter, the applicant invoked arbitration under Section 21 of the Arbitration and Conciliation Act, 1996, by notice dated 2 March 2026 and nominated a former High Court Judge as sole arbitrator.
Source reference: para. 6SECL neither accepted the nomination nor proposed an alternative arbitrator.
Source reference: para. 6Issues
Whether the applicant had established the existence of an arbitration agreement and fulfilled the contractual pre-arbitration requirements so as to invoke the jurisdiction of the Court under Section 11(6) of the Arbitration and Conciliation Act, 1996.
Source reference: paras. 1–2, 5–6Whether, in view of the respondents’ failure to concur in the applicant’s nomination and the parties’ subsequent consensus, a sole arbitrator should be appointed by the Court.
Source reference: paras. 6–10Whether the merits of the applicant’s monetary claims and SECL’s recoveries required adjudication at the Section 11 stage.
Source reference: para. 6Law Applied
Section 7 of the Arbitration and Conciliation Act, 1996 requires an arbitration agreement in writing; Clause 13A of the agreement constituted such an arbitration agreement.
Source reference: para. 2Section 21 governs commencement of arbitral proceedings upon receipt of a request for reference to arbitration.
Source reference: para. 6Section 11(6) empowers the Court to appoint an arbitrator where the agreed appointment procedure has failed, including where a party fails to act as required under that procedure.
Source reference: paras. 1 and 6The contractual mechanism under Clauses 13 and 13A required exhaustion of the in-house dispute-resolution process before arbitration could be invoked.
Source reference: paras. 2 and 5At the appointment stage, the Court was concerned with constituting the arbitral tribunal and did not adjudicate the merits of the parties’ claims, recoveries or counterclaims.
Source reference: para. 6Reasoning
The Court found that the agreement contained a valid arbitration clause and that the applicant had invoked and exhausted both stages of the contractual in-house mechanism.
Source reference: paras. 2 and 5The applicant thereafter issued a valid notice under Section 21 and called upon SECL to concur in the appointment of an arbitrator.
Source reference: para. 6SECL failed to respond or nominate an alternative, thereby giving rise to the occasion for action under Section 11(6).
Source reference: para. 6The subsequent “Speaking Order” issued by SECL did not extinguish the disputes because it was issued by an officer of a party to the dispute and merely confirmed SECL’s own position; the underlying claims and recoveries remained matters for arbitral adjudication.
Source reference: para. 6Since both parties ultimately agreed that a retired District Judge could act as arbitrator and specifically proposed Mr. Ashok Kumar Panda, the Court accepted that consensus and appointed him as sole arbitrator.
Source reference: paras. 7–10Holding
The arbitration request was allowed under Section 11(6) of the Arbitration and Conciliation Act, 1996.
Mr. Ashok Kumar Panda, retired District Judge, was appointed as the sole arbitrator to adjudicate the disputes between the parties.
Source reference: para. 10The Registry was directed to communicate the order to the arbitrator, and his remuneration was to be settled by mutual consent of the parties.
Source reference: paras. 11–12The Court did not decide the merits of the applicant’s monetary claims or SECL’s alleged recoveries, leaving those issues for determination by the arbitral tribunal.
Source reference: para. 6Acts & Sections Cited
4 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19964
Original Court PDF
S Kumars AssociatesvsSouth Eastern Coalfields Limited SECL
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
