01

Facts

Ramani J. and P. Judith Kalaiselvi filed writ petitions challenging an order dated 24 March 2025 concerning their land and buildings in Survey No. 200, and sought protection against demolition, dispossession, or interference with their possession

Source reference: p. 2; p. 3, para. 1

The connected contempt petition alleged non-compliance with an earlier order directing the District Collector and Tahsildar to remove encroachments from the same survey number within twelve weeks

Source reference: p. 3, para. 2; p. 4, para. 3

During the contempt proceedings, the District Collector granted pattas in favour of the writ petitioners.

Source reference: p. 4, para. 5

The contempt petitioner then stated that he had no objection to closure of the contempt petition, while seeking liberty to pursue his remedy in accordance with law

Source reference: p. 4, para. 5; p. 5, para. 5
02

Issues

1. Whether the contempt petition alleging non-compliance with the order dated 21 December 2023 should continue after pattas were granted to the writ petitioners and the contempt petitioner had no objection to its closure.

Source reference: p. 4, paras. 3, 5; p. 5, para. 6

2. Whether the writ petitions challenging the order dated 24 March 2025 required adjudication in light of the subsequent development concerning the grant of pattas.

Source reference: p. 2; p. 3, para. 1; p. 5, para. 6
03

Law Applied

The writ petitions were brought under Article 226 of the Constitution of India.

Source reference: p. 2

The Court also considered the earlier order in W.P.(MD) No. 30727 of 2023, which had directed removal of encroachments within twelve weeks and initiation of appropriate action in accordance with law.

Source reference: p. 4, para. 3

The order does not identify or apply any further statute, precedent, or substantive legal doctrine; the matters were disposed of on the basis of the subsequent development and the contempt petitioner’s submission.

Source reference: p. 5, paras. 5–6
04

Reasoning

The Court noted that the contempt petition concerned alleged non-compliance with the earlier direction to remove encroachments, but that pattas had subsequently been granted to the writ petitioners.

Source reference: p. 5, paras. 5–6

Given this development, and the contempt petitioner’s stated lack of objection to closure while reserving liberty to pursue other remedies, the Court closed the contempt proceedings and granted that liberty.

Source reference: p. 5, paras. 5–6

It also closed the connected writ petitions without deciding the merits of the challenge to the impugned order.

Source reference: p. 5, para. 6
05

Holding

The Court closed Cont.P.(MD) No. 2399 of 2024 and granted the contempt petitioner liberty to work out his remedy in accordance with law.

It also closed W.P.(MD) Nos. 9366 and 9367 of 2025 and the connected miscellaneous petitions; no substantive determination of the writ petitioners’ challenge was made.

Source reference: p. 5, para. 6
Madras High Court

Original Court PDF

Ramani JvsThe Divisional Engineer (Hig

Madras High Court · September 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment