Facts
The Petitioner, a registered Class ‘C’ contractor, was awarded multiple contracts between 2022 and 2024 for Piped Water Supply Schemes under the Jal Jeevan Mission (JJM).
Source reference: para. 3Following the execution of works and submission of bills, an internal audit conducted by Respondent No. 4 in April 2024 raised objections regarding the rate analysis of Functional Household Tap Connections (FHTC).
Source reference: para. 3Consequently, Respondent No. 2 issued a circular in December 2024 directing the retrospective revision of contract rates and the recovery of ₹1,871 per connection, leading to the withholding of the Petitioner’s final bills and security deposits.
Source reference: para. 3The Petitioner challenged these actions under Article 226, alleging a violation of natural justice and promissory estoppel, and sought the release of outstanding payments.
Source reference: para. 2, 4Issues
1. Whether the High Court, in its writ jurisdiction, can adjudicate a dispute involving the unilateral revision of contract rates and non-payment of dues arising from a concluded commercial contract.
Source reference: para. 5, 82. Whether the impugned actions of the Respondents were sufficiently arbitrary or mala fide to warrant judicial interference in a contractual matter.
Source reference: para. 8Law Applied
The Court primarily relied on the principles of judicial restraint in contractual and commercial matters as articulated by the Supreme Court in Tata Motors Limited v. The Brihan Mumbai Electric Supply & Transport Undertaking (BEST) and Others (2023).
Source reference: para. 7The core rule established is that writ courts should not interfere in contractual disputes unless a "clear-cut case of arbitrariness, mala fides, or irrationality" is demonstrated.
Source reference: para. 7The Court further applied the doctrine that disputes involving factual determinations—such as work completion, quality, and measurement—are civil in nature and should be resolved through alternative remedies like arbitration or civil suits rather than under Article 226.
Source reference: para. 5, 8Reasoning
The Court observed that the grievance pertains to the non-release of contractual dues and the retrospective adjustment of rates based on audit observations.
Source reference: para. 8Applying the Tata Motors precedent, the Court reasoned that the petitioner failed to demonstrate any exceptional circumstances, such as gross arbitrariness or palpable irrationality in the decision-making process.
Source reference: para. 8The Court noted that the dispute involves complex factual determinations regarding the measurement and verification of work, which fall squarely within the domain of private civil law.
Source reference: para. 8It emphasized that judicial review is limited in technical and commercial matters, and courts must allow "fair play in the joints" to the government in managing public contracts.
Source reference: para. 7Consequently, the Court found the petition to be a surrogate for a money suit.
Source reference: para. 8Holding
The Court dismissed the writ petition, holding that the dispute was purely contractual and lacked the requisite element of public law arbitrariness to justify interference under Article 226.
The Court concluded that the Petitioner's remedy lies in availing appropriate alternative legal proceedings, such as a civil suit or arbitration, for the recovery of alleged dues.
Source reference: para. 8All reliefs sought were denied.
Source reference: para. 9Original Court PDF
BIRBAL NISHADvsSTATE OF CHHATTISGARH
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in