Delhi High Court
Arbitration and MediationAdministrative and Public Law

Writ jurisdiction is ordinarily declined for arbitrable contractual disputes with an efficacious alternative remedy.

Kaushal Sharma vs National Highway And Infrastructure Development Corporations Nhidcl

Delhi High CourtJUDGMENT: October 09, 20262 MIN READSOURCE JUDGMENT
Writ jurisdiction is ordinarily declined for arbitrable contractual disputes with an efficacious alternative remedy.. Kaushal Sharma vs National Highway And Infrastructure Development Corporations Nhidcl. Delhi High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner challenged NHIDCL’s notice dated 25 September 2026, issued under Clause 23.1(ii) of the EPC contract, contending that he had already terminated the contract after issuing a notice of intention to terminate on 15 September 2026. He sought to restrain consequential action, including encashment of his Performance Bank Guarantee, and to prevent NHIDCL from engaging another contractor or creating third-party rights in respect of the works.

Source reference: p. 2

NHIDCL argued that the dispute was contractual and should be resolved through the contract’s dispute-resolution mechanism, including arbitration. The parties did not dispute that the issues were arbitrable.

Source reference: p. 2
02

Issues

1. Whether the Court should exercise its jurisdiction under Article 226 to determine a contractual dispute that the parties accept is arbitrable.

Source reference: pp. 2–3

2. Whether the petitioner’s requested interim relief concerning the Performance Bank Guarantee and the works should instead be pursued through the available arbitral remedies.

Source reference: p. 3
03

Law Applied

Article 226 confers discretionary jurisdiction, which the High Court would ordinarily decline to exercise in a contractual dispute where the parties have agreed to a specific dispute-resolution mechanism, particularly arbitration.

Source reference: pp. 3–5

Under Joshi Technologies International Inc. v. Union of India, (2015) 7 SCC 728, contractual disputes without a public-law element, disputes involving serious contested facts, and contractual monetary claims will normally be left to the remedies provided by contract or ordinary law; the existence of an alternative remedy is not an absolute bar, but may warrant refusal of writ relief.

Source reference: pp. 3–5

The Court also noted that interim relief concerning the Performance Bank Guarantee could be sought in proceedings under Section 9 of the Arbitration and Conciliation Act, 1996.

Source reference: p. 3
04

Reasoning

The central dispute—whether the petitioner had validly terminated the EPC contract before NHIDCL issued its notice—required determination of contractual rights and was accepted by both parties as arbitrable.

Source reference: p. 2

The Court found no exceptional circumstance requiring it to intervene under Article 226. Because an alternative arbitral remedy was available, including an application under Section 9 for interim protection concerning the Performance Bank Guarantee, the contractual nature of the dispute weighed against exercising writ jurisdiction.

Source reference: pp. 3, 6
05

Holding

The Court declined to exercise its discretionary jurisdiction under Article 226.

The Court disposed of the petition, leaving the petitioner at liberty to pursue remedies available in law, including the appropriate arbitral remedies. It did not determine the validity of either party’s termination or grant the substantive relief sought.

Source reference: p. 6
06

Acts & Sections Cited

1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19961

Delhi High Court

Original Court PDF

Kaushal SharmavsNational Highway And Infrastructure Development Corporations Nhidcl

Delhi High Court · October 09, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment