Madras High Court
Arbitration and MediationProperty and Real Estate Law

16-year wait for fair land compensation violates Article 300A, Madras High Court says while dismissing NHAI appeals

THE PROJECT DIRECTOR vs MALARKODI

Madras High CourtJUDGMENT: September 28, 20262 MIN READSOURCE JUDGMENT
16-year wait for fair land compensation violates Article 300A, Madras High Court says while dismissing NHAI appeals. THE PROJECT DIRECTOR vs MALARKODI. Madras High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The National Highways Authority of India (NHAI) appealed under Section 37 of the Arbitration and Conciliation Act, 1996, against the dismissal of its Section 34 applications challenging arbitral awards concerning land acquisition compensation.

Source reference: pp. 3–7

The awards were received at the NHAI office on 05.01.2019, and the Section 34 applications were filed on 05.04.2019.

Source reference: pp. 3–7

The Principal District Judge held the applications to be one day late and also considered the challenges on their merits.

Source reference: pp. 3–7

NHAI argued that the receipt date should be excluded when calculating limitation and that 05.01.2019 was a Saturday; the landowners disputed that the office was closed that day.

Source reference: pp. 3–7

The land acquisition proceedings had originated in 2008, with notification under Section 3G(1) of the National Highways Act, 1956, in 2010.

Source reference: p. 7
02

Issues

Whether the Section 34 applications were filed within the limitation period under Section 34(3), given receipt of the awards on 05.01.2019 and filing on 05.04.2019.

Source reference: pp. 3–7

Whether the appellate court should interfere with the arbitral awards in light of the District Judge’s findings on the merits of NHAI’s challenges.

Source reference: pp. 6–8
03

Law Applied

Section 34(3) of the Arbitration and Conciliation Act, 1996 provides a three-month period to apply for setting aside an arbitral award, calculated from receipt of the award; the Court treated the date of receipt as excluded when calculating that period.

Source reference: p. 6

Appeals from the order on a Section 34 application were brought under Section 37(1) and (2) of the Act.

Source reference: p. 2

The Court also observed that prolonged non-payment of fair compensation for acquired property implicates the constitutional protection under Article 300-A.

Source reference: p. 7
04

Reasoning

The Court found that the awards were received on 05.01.2019 and the applications were filed on 05.04.2019.

Source reference: p. 6

Because the date of receipt was not to be counted, the District Judge’s conclusion that the applications were one day late was erroneous.

Source reference: p. 6

The Court nevertheless declined to set aside the awards: it noted that the lower court had found sufficient notice of the arbitral proceedings and that NHAI had failed to appear before the Arbitrator; it also found no basis to disturb the findings against NHAI on its challenges to the evidence and its non-party contention.

Source reference: pp. 7–8
05

Holding

The Court held that the limitation finding against NHAI was erroneous, but that error did not warrant interference with the awards because NHAI’s challenges on the merits failed.

All three appeals were dismissed, with no order as to costs; the connected miscellaneous petitions were closed.

Source reference: p. 8
06

Acts & Sections Cited

2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19962

Madras High Court

Original Court PDF

THE PROJECT DIRECTORvsMALARKODI

Madras High Court · September 28, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment