01Facts
The Karnataka Housing Board acquired the petitioners’ lands for a residential layout through notifications under Sections 4(1) and 6(1) of the Land Acquisition Act, 1894. An award was passed, compensation was paid to the petitioners in 2014, and possession was delivered to the respondents
pp. 5–6The petitioners claimed that a 50:50 scheme—under which landowners receive 50% of the developed land instead of compensation—had been applied in other parts of Karnataka. They sought a mandamus directing the respondents to extend that scheme to their acquired lands, relying on government notifications, including one dated 13 December 2022
p. 6They stated they were willing to refund the compensation with applicable interest, subject to the scheme’s terms and conditions
p. 702Issues
i.1. Whether the petitioners were entitled to a direction requiring the respondents to allot them 50% of the developed land under the 50:50 scheme
pp. 5–6ii.2. Whether the respondents should be directed to consider the petitioners’ representations under the relevant notifications, subject to the scheme’s conditions and limitations
pp. 7–803Law Applied
The acquisition was undertaken under Sections 4(1) and 6(1) of the Land Acquisition Act, 1894
p. 5The Court referred to government notifications concerning the 50:50 scheme but did not determine that the petitioners had an enforceable right to its benefits. Any entitlement was left to be assessed under the applicable notifications, subject to their limitations and conditions
pp. 6–8Provisions in the judgment · 2
Land Acquisition Act, 1894 Section 4Section 6
04Reasoning
The Court noted the petitioners’ reliance on the 50:50 scheme and their willingness to refund the compensation with applicable interest
pp. 6–7It did not decide whether the petitioners qualified for the scheme or grant the requested allotment. Instead, it left the question of entitlement to the competent respondents, directing them to consider representations in accordance with the relevant notifications and applicable conditions
pp. 7–805Holding
The petition was disposed of. The petitioners were directed to submit representations under the relevant notifications, and Respondents 2 and 3 were directed to consider them according to law, if the petitioners were entitled to the scheme, subject to all limitations and conditions.
pp. 7–8The respondents were to act as expeditiously as possible and within three months, and to file a compliance report after that period
pp. 7–8Original Court PDF