Gujarat High Court

A consumer who fails to appeal a supplementary electricity bill cannot challenge it in a recovery suit.

MIRA ICE FACTORY THROUGH PARTNER vs PASCHIM GUJARAT VIJ COMPANY LTD

Gujarat High CourtJUDGMENT: August 04, 20263 MIN READSOURCE JUDGMENT
A consumer who fails to appeal a supplementary electricity bill cannot challenge it in a recovery suit.. MIRA ICE FACTORY THROUGH PARTNER vs PASCHIM GUJARAT VIJ COMPANY LTD. Gujarat High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

On 17 December 2003, Paschim Gujarat Vij Company Ltd. (“PGVCL”) conducted a surprise inspection at the appellant’s Mira Ice Factory and allegedly detected malpractice involving the electricity meter, seals and wiring.

Source reference: p.5, para.7

The meter was sealed and sent for laboratory examination; the laboratory report recorded that the meter seal was tampered with and duplicated.

Source reference: p.5, para.7

Applying the ABCD formula under the applicable Conditions of Supply of Electrical Energy, PGVCL raised a supplementary bill of Rs.8,35,364.09 on 19 April 2005 and subsequently disconnected the electricity supply for non-payment.

Source reference: p.2, para.3

PGVCL instituted Special Civil Suit No.89 of 2005 before the Principal Senior Civil Judge, Porbandar, seeking recovery of Rs.13,16,158.75, comprising the principal supplementary bill, delayed-payment charges and other amounts, with interest at 18% per annum.

Source reference: p.2, paras.3–3.1

The appellant denied the alleged malpractice and challenged the maintainability and correctness of the claim.

Source reference: p.2, para.3.2

The trial court partly decreed the suit and directed payment of Rs.8,35,364.09 with 6% delayed-payment charges from the date of filing of the suit until realisation.

Source reference: p.1, para.2

The appellant preferred the present appeal under Section 96 of the Code of Civil Procedure.

Source reference: p.3, para.3.3
02

Issues

1. Whether the appellant could challenge the supplementary electricity bill and the alleged meter malpractice as a defence in the recovery suit when the appellant had not availed the appellate remedy provided under the Conditions of Supply of Electrical Energy?

Source reference: pp.5–8, para.9

2. Whether PGVCL had established the alleged tampering and duplication of the meter seal and was entitled to recover the supplementary bill assessed under the ABCD formula?

Source reference: p.5, para.7; pp.7–8, para.9

3. Whether the trial court’s decree limited to Rs.8,35,364.09 with 6% delayed-payment charges was liable to be set aside in the appellant’s first appeal?

Source reference: p.1, para.2; p.9, paras.10–11
03

Law Applied

The Court exercised appellate jurisdiction under Section 96 of the Code of Civil Procedure.

Source reference: p.3, para.3.3

Under the Conditions of Supply of Electrical Energy, a consumer found to have indulged in malpractice or dishonest abstraction of electricity is liable to additional charges assessed according to the prescribed ABCD formula, and an aggrieved consumer must challenge the supplementary bill before the designated Appellate Authority.

Source reference: pp.6–8, para.9

Relying on Paschim Gujarat Vij Company Ltd. v. Bhikhabhai Arjanbhai Varu, Second Appeal No.11 of 2012, and the authorities cited therein—Vrajlal Devjibhai v. GEB, First Appeal No.2506 of 2003; Punjab State Electricity Board v. Ashwani Kumar, (1997) 5 SCC 120; and Hyderabad Vanaspathi Ltd. v. A.P. State Electricity Board, (1998) 4 SCC 470—the Court applied the rule that, where the Conditions of Supply provide a specific appellate mechanism for disputing a supplementary bill, a consumer who fails to invoke that remedy cannot subsequently raise the same challenge by way of defence in a recovery suit.

Source reference: pp.6–8, para.9

The cited precedents further recognise the validity of the electricity board’s prescribed machinery for assessment and recovery of charges arising from malpractice.

Source reference: pp.7–8, para.9
04

Reasoning

The Court found that PGVCL’s officers had produced the consumer’s electricity-connection documents, the inspection material and the laboratory report.

Source reference: p.5, para.7

The laboratory report specifically recorded that the meter seal was tampered with and duplicated, and the appellant had not seriously contested this evidence.

Source reference: p.5, para.7

The supplementary bill was accordingly prepared under the prescribed ABCD formula.

Source reference: p.5, para.6

Applying the rule that an unchallenged supplementary bill attains finality where the consumer fails to use the contractual appellate remedy, the Court held that the appellant could not reopen the assessment or dispute the underlying malpractice in the recovery proceedings.

Source reference: pp.5–8, para.9

Although PGVCL argued that the entire claim ought to have been decreed, the present appeal was by the appellant against the trial court’s partly favourable decree, and the High Court found no ground to interfere with that decree.

Source reference: p.9, paras.10–11
05

Holding

The High Court dismissed the appeal and upheld the judgment and decree dated 20 November 2012 in Special Civil Suit No.89 of 2005, under which the appellant was directed to pay PGVCL Rs.8,35,364.09 with 6% delayed-payment charges from the date of filing of the suit until realisation.

The Court discontinued any interim relief granted earlier and directed the Registry to return the Record and Proceedings to the concerned court, if any.

Source reference: p.10, paras.12–13
06

Acts & Sections Cited

1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Code of Civil Procedure, 19081

Gujarat High Court

Original Court PDF

MIRA ICE FACTORY THROUGH PARTNERvsPASCHIM GUJARAT VIJ COMPANY LTD

Gujarat High Court · August 04, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment