Delhi High CourtArbitration and MediationContract Law

### A contract terminable only for cause and subject to a cure period is not "determinable" under Section 14(d).

Mahajan Imaging Pvt. Ltd. v. Pushpawati Singhania Research Institute & Anr. [O.M.P.(I) (COMM.) 29/2026]

### A contract terminable only for cause and subject to a cure period is not "determinable" under Section 14(d).. Mahajan Imaging Pvt. Ltd. v. Pushpawati Singhania Research Institute & Anr. [O.M.P.(I) (COMM.) 29/2026]. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Radiology Services Agreement is "in its nature determinable" under Section 14(d) of the Specific Relief Act (SRA), thereby barring specific performance and interim injunctions

The court held

The Court answered the issues in the negative regarding the statutory bars and in the affirmative regarding the triple test.

It also directed

It held that the Agreement is not determinable under Section 14(d) SRA because it requires a cure period for termination

The Court granted the petition, staying the Impugned Termination Notice dated 02.01.2026 and directing the parties to maintain *status quo* as it existed prior to the notice

The Respondents were directed to adhere to the contractual terms, and all rights were reserved for the Arbitral Tribunal

01Facts

The Petitioner (Mahajan Imaging) and Respondent No. 1 (PSRI Hospital) entered into a Radiology Services Agreement on 02.05.2016 for a 15-year term

p. 3

On 02.01.2026, the Respondent issued a Termination Notice alleging material breaches of statutory and contractual obligations (PC-PNDT Act and Atomic Energy Act violations), effective 02.02.2026

p. 4

The Petitioner challenged the notice, asserting the Agreement required a mandatory 45-day cure period under Clause 10.2(a) which was never provided

p. 4, 8

The Petitioner filed this Section 9 petition seeking an interim injunction against the termination pending arbitration

p. 2

02Issues

i.1. Whether the Radiology Services Agreement is "in its nature determinable" under Section 14(d) of the Specific Relief Act (SRA), thereby barring specific performance and interim injunctions

p. 11

ii.2. Whether the continuous nature of the services under the Agreement attracts the bar on specific performance under Section 14(b) of the SRA due to the need for constant judicial supervision

p. 6, 21

iii.3. Whether the Petitioner satisfied the "triple test" (prima facie case, balance of convenience, and irreparable injury) for the grant of interim protection

p. 9, 38

03Law Applied

The court primarily applied Section 14 of the Specific Relief Act, 1963, which lists contracts not specifically enforceable, including those involving continuous duties and those determinable in nature

p. 11

It relied heavily on the Supreme Court's classification in *K.S. Manjunath v. Moorasavirappa*, which distinguishes between contracts terminable "at will" (determinable) and those terminable only "for cause" with a cure notice (not determinable)

¶ 29, 31

Precedents like *DLF Home Developers Ltd. v. Shipra Estate Ltd.* [para. 29] and *ArcelorMittal Nippon Steel (India) Ltd. v. Essar Bulk Terminal Ltd.* [para. 25] were utilized to define the scope of Section 9 of the Arbitration and Conciliation Act, 1996, and the parameters for interim relief.

¶ 29, 25

Provisions in the judgment · 2 · Linked ones open on LawLens

Specific Relief Act, 1963 Section 14

Arbitration and Conciliation Act, 1996 Section 9

04Reasoning

The Court reasoned that Clause 10.2(a) of the Agreement did not grant an "at-will" right to terminate; rather, it required a "material breach" and a 45-day "cure period"

pp. 19-20

Following *K.S. Manjunath*, the Court held that since the Respondent could not terminate the contract so long as the Petitioner remained willing to perform and was not in default (until the cure period lapsed), the contract was not "inherently determinable"

p. 20

Regarding Section 14(b) SRA, the Court found that staying a termination does not require day-to-day judicial management of radiology services, as the parties had functioned independently for nine years

p. 21

On the merits, the Court observed that the Respondent prima facie "put the cart before the horse" by terminating without adhering to the mandatory 45-day cure notice period

pp. 39-40

The Court found that the loss of the Petitioner’s commercial rights for the remaining five-year tenure and potential reputational harm constituted irreparable injury

pp. 40-41

05Holding

The Court answered the issues in the negative regarding the statutory bars and in the affirmative regarding the triple test.

It held that the Agreement is not determinable under Section 14(d) SRA because it requires a cure period for termination

p. 20

The Court granted the petition, staying the Impugned Termination Notice dated 02.01.2026 and directing the parties to maintain *status quo* as it existed prior to the notice

p. 41

The Respondents were directed to adhere to the contractual terms, and all rights were reserved for the Arbitral Tribunal

pp. 41-42
Delhi High Court

Original Court PDF

Mahajan Imaging Pvt. Ltd. v. Pushpawati Singhania Research Institute & Anr. [O.M.P.(I) (COMM.) 29/2026]

Delhi High Court · no citation

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment