Delhi High Court
Arbitration and MediationContract Law

A contractual bar cannot absolutely exclude damages for employer-caused prolongation.

Union Of India vs M/S. Navayuga Engineering Co. Ltd. & Anr.

Delhi High CourtJUDGMENT: August 19, 20264 MIN READSOURCE JUDGMENT
A contractual bar cannot absolutely exclude damages for employer-caused prolongation.. Union Of India vs M/S. Navayuga Engineering Co. Ltd.  & Anr.. Delhi High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Union of India awarded M/s Navayuga Engineering Co. Ltd. a contract for construction of the Naraina T-Point flyover, New Delhi, under Agreement No. 21/EE/DS & CM/PWD/06-07.

Source reference: p.1–2, paras. 2–4

The stipulated completion period was 21 months, from 14 March 2007 to 13 December 2008. The project was ultimately extended until 15 January 2013 through six extensions, without levy of liquidated damages.

Source reference: p.1–2, paras. 2–4

The contractor alleged that the prolongation resulted from delays attributable to the Union of India and claimed compensation for additional expenditure, including idling of machinery, site establishment and expenses, bank-guarantee extensions, head-office overheads, inspection facilities, and interest on mobilisation advance.

Source reference: p.2–3, para. 5

The learned Sole Arbitrator awarded Rs.1,07,02,697 under Claim No. 1; rejected Claim No. 2; awarded Rs.45,51,450 under Claim No. 3(a); and awarded Rs.1,70,45,681 collectively under Claims 3(b) to 3(g).

Source reference: p.3–4, paras. 6–7

The Union of India challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, principally insofar as it allowed Claims 3(a) to 3(g).

Source reference: p.4, para. 8
02

Issues

Whether the arbitral tribunal could award compensation for prolongation-related expenditure despite Special Conditions Clauses 3.18 and 3.52, which were relied upon as barring claims for idle establishment, labour, machinery, equipment and tools?

Source reference: p.4–5, paras. 9–10; p.8–12, paras. 21–31

Whether the tribunal’s quantification of compensation under Claims 3(a) to 3(g) was unsupported by evidence, arbitrary or perverse because it did not separately calculate the loss attributable to the 568 days of delay assigned to the Union of India?

Source reference: p.5–6, paras. 11–14; p.12–15, paras. 32–39

Whether the tribunal acted within the permissible scope of arbitral assessment by adopting percentage-based estimates, having rejected the contractor’s claimed figures as exaggerated?

Source reference: p.15–20, paras. 40–46
03

Law Applied

A Section 34 court does not sit in appeal over an arbitral award, reappreciate evidence, or substitute its own view for that of the tribunal; interference is permissible only on recognised statutory grounds, including patent illegality, perversity, conflict with contractual terms, or conclusions unsupported by the record.

Source reference: p.7, paras. 18–20

The Court relied on DMRC Ltd. v. Delhi Airport Metro Express (P) Ltd., PSA Sical Terminals (P) Ltd. v. V.O. Chidambaranar Port Trust, State of Chhattisgarh v. Sal Udyog Pvt. Ltd., and Associate Builders v. Delhi Development Authority.

Source reference: p.7, para. 20

Under Sections 23, 55 and 73 of the Indian Contract Act, 1872, a contractual term that absolutely extinguishes a substantive right to claim damages for breach may be unlawful and void, while compensation may be awarded for loss caused by breach, subject to proof and mitigation.

Source reference: p.9–12, paras. 26–30

The Court relied on Asian Techs Ltd. v. Union of India, Simplex Concrete Piles (India) Ltd. v. Union of India, and MBL Infrastructure Ltd. v. Delhi Metro Rail Corporation Ltd. for the principle that clauses restricting prolongation claims do not necessarily bar an arbitrator from adjudicating damages claims and cannot render the injured party remediless.

Source reference: p.9–12, paras. 26–30

The tribunal has latitude to select a reasonable method for quantifying damages where precise computation is impracticable; some estimation based on industry standards, CPWD schedules or MORTH data may be permissible.

Source reference: p.15–20, paras. 40–44

An award need not resemble a judicial judgment or explain every reasoning step, provided its reasoning is intelligible when read as a whole.

Source reference: p.20–21, paras. 47–49
04

Reasoning

The Court held that the tribunal had expressly considered Clauses 3.18 and 3.52 and had found that they could not operate as an absolute bar to damages under Sections 23, 55 and 73 of the Indian Contract Act.

Source reference: p.8–12, paras. 22–31

The tribunal also examined the contractual extensions, shifting of milestones, absence of liquidated damages and the parties’ respective responsibility for delay; therefore, it had not ignored the contractual provisions or exceeded its jurisdiction.

Source reference: p.8–12, paras. 22–31

On quantification, the Court acknowledged that the tribunal could have separately apportioned the loss according to the 568 days attributable to the Union of India.

Source reference: p.13–15, paras. 35–39

However, the tribunal had found the contractor’s figures exaggerated, considered deficiencies in the evidence, recognised that the contractor had also contributed to the delay, and assessed only a reduced amount rather than awarding the claimed sums in full.

Source reference: p.13–15, paras. 35–39

For Claim 3(a), it awarded 5% of the amount claimed.

Source reference: p.18–20, paras. 42–44

For Claims 3(b) to 3(g), it considered CPWD and MORTH overhead percentages and, after the Union of India failed to provide the requested weighted average, awarded 15% of the aggregate sub-claims—approximately 1.74% of the tendered amount.

Source reference: p.18–20, paras. 42–44

The Court found that these percentages were reasoned estimates and not arbitrary guesswork.

Source reference: p.19–21, paras. 44–49

The absence of a separate day-wise calculation did not, by itself, establish perversity or patent illegality.

Source reference: p.19–21, paras. 44–49
05

Holding

The Court answered the issues against the Union of India.

It held that Clauses 3.18 and 3.52 did not constitute an absolute bar to the contractor’s claims for damages arising from prolongation attributable to the employer.

Source reference: p.20–21, paras. 49–51

The tribunal’s percentage-based assessment under Claims 3(a) to 3(g), read with its findings on exaggerated claims, mitigation and shared delay, was neither perverse nor patently illegal.

Source reference: p.20–21, paras. 49–51

The challenge to Claims 3(a) to 3(g) was rejected, the petition under Section 34 was dismissed, and all pending applications were disposed of.

Source reference: p.21–22, paras. 50–53
06

Acts & Sections Cited

5 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19962

Indian Contract Act, 18723

Delhi High Court

Original Court PDF

Union Of IndiavsM/S. Navayuga Engineering Co. Ltd. & Anr.

Delhi High Court · August 19, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment