Facts
The Appellant was awarded a five-year contract for the upgradation, maintenance and management of the AC Upper Class Waiting Room at Chhatrapati Shivaji Maharaj Terminus, Mumbai, along with allied passenger facilities.
Source reference: para. 3–4He invested approximately ₹40,00,000 in the project and claimed that no complaints had been made regarding his performance during the contractual period.
Source reference: para. 3–4Relying on Railway Board policies, including the Delhi Division Model and Circular No. 11 of 2022, the Appellant sought renewal for a further five years.
Source reference: para. 5.1; para. 12While his representations remained undecided, the Respondents floated a fresh tender. The Respondents granted two short-term extensions, but at enhanced licence fees.
Source reference: para. 5.1; para. 12The Appellant therefore sought interim protection under Section 9 of the Arbitration and Conciliation Act, 1996. The learned Single Judge rejected the petition on 3 August 2026, principally holding that the Appellant had no enforceable right to a further extension. The present appeal was filed under Section 37(1)(b) of the Act.
Source reference: para. 1Issues
Whether the Appellant’s contract was governed by Clause 8.1(v) of Railway Board Circular No. 11 of 2022, thereby entitling him to a contractual duration of ten years or a further five-year extension.
Source reference: para. 6; para. 9–10Whether the Appellant could claim renewal or extension of the contract as a matter of right on the basis of the Delhi Division Model, Railway Board policies, legitimate expectation, promissory estoppel, or the Appellant’s investment and satisfactory performance.
Source reference: para. 5.1–5.2; para. 14Whether the learned Single Judge exceeded the permissible scope of proceedings under Section 9 by making findings on the disputed contractual issues while refusing interim protection.
Source reference: para. 2; para. 13Whether the impugned order disclosed any error warranting appellate interference under Section 37(1)(b).
Source reference: para. 1; para. 16–17Law Applied
The Court applied Sections 9 and 37(1)(b) of the Arbitration and Conciliation Act, 1996, governing interim measures and appeals from orders granting or refusing such measures.
Source reference: no citationIt relied on Clause 8 of Railway Board Circular No. 11 of 2022, which prescribed a five-year duration for “AC Waiting Hall Management” under Clause 8.1(iii), while the ten-year period under Clause 8.1(v)(b) applied only to pay-and-use toilets operated under the ROMT model.
Source reference: para. 9–10Clause 9 of the Circular further provided that extensions of contracts awarded through e-auction would normally not be permitted, save for temporary extensions, generally not exceeding three months, in specified circumstances.
Source reference: para. 11The Court also relied on M.P. Road Development Corporation Ltd. v. Jabalpur Corridor (P) Ltd., 2026 SCC OnLine SC 1001, for the principle that appellate intervention in arbitration matters is narrowly circumscribed and is not justified merely because another interpretation of the facts or contract is possible.
Source reference: para. 15Reasoning
The Court held that the Appellant had incorrectly relied on Clause 8.1(v) of Circular No. 11 of 2022. That provision concerned pay-and-use toilets, whereas the Appellant’s contract expressly related to AC Waiting Hall Management, which fell under Clause 8.1(iii) and carried a five-year contractual duration.
Source reference: para. 10–11The contractual scope and the applicable policy therefore did not create any entitlement to an additional five-year term. The two extensions already granted were temporary extensions contemplated by the policy and did not establish a right of renewal.
Source reference: para. 11–12Although the Appellant’s expectation arising from his investment and performance was understandable, the fixed contractual term and the discretionary nature of any extension prevented such expectation from becoming an enforceable right.
Source reference: para. 14The Court further found that the Single Judge had considered the relevant contractual and policy issues without exceeding the scope of Section 9, and that no error warranting interference under Section 37 was demonstrated.
Source reference: para. 13; para. 16Holding
The contract was for five years under Clause 8.1(iii) of Circular No. 11 of 2022, and the Appellant was not entitled as of right to a further five-year extension.
The legitimate expectation arising from his investment and satisfactory performance could not override the contractual terms or confer a right to renewal.
Source reference: para. 14Finding no legal or factual error in the order refusing interim relief under Section 9, the Division Bench dismissed the appeal under Section 37(1)(b), with no order as to costs.
Source reference: para. 16–17Acts & Sections Cited
3 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19963
Original Court PDF
Shivmoorat Kushwaha, Proprietor Of Ms Namah EnterprisesvsUnion Of India
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
