Facts
The petitioner alleged that CESC’s electricity meter, electric line, and other electrical installations situated on his premises were being used to supply electricity to the private respondents, his nephew(s).
Source reference: paras. 1–3; pp. 1–2The petitioner stated that he had initially permitted the installation but, after the relationship deteriorated, requested its removal because CESC personnel and other persons frequently visited the premises for inspection, causing nuisance and disturbance.
Source reference: paras. 1–3; pp. 1–2CESC submitted that it was willing to shift the installations to premises occupied by the private respondents, subject to an application for a new supply, production of tax or other relevant premises documents, and an application for removal of the existing meter in the private respondent’s name.
Source reference: para. 4; p. 2The private respondents agreed to bear the shifting charges but disputed the bill of Rs. 2,52,777/- as exorbitant.
Source reference: para. 5; p. 3The Court found that the petitioner owned the premises and that CESC had identified an alternative route for supplying electricity without disturbing the petitioner’s property.
Source reference: paras. 7–9; p. 3Issues
Whether CESC could be directed to shift the electrical line and installations from the petitioner’s premises when an alternative means of supplying electricity to the private respondents was available.
Source reference: paras. 7–10; pp. 3–4Whether the shifting could be made subject to the private respondents’ compliance with CESC’s formalities and payment of lawful charges, and whether failure to comply could result in disconnection of supply.
Source reference: paras. 11–12; p. 4Whether the distribution licensee’s duty to supply electricity under Section 43 of the Electricity Act, 2003 required it to continue supplying the private respondents through the petitioner’s premises despite the availability of an alternative route.
Source reference: para. 13; p. 4Law Applied
The Court applied Section 43 of the Electricity Act, 2003, which imposes a duty on a distribution licensee to supply electricity to an applicant or consumer in accordance with the statutory requirements.
Source reference: para. 13; p. 5The Court held that this duty does not extend to maintaining supply through a route that disturbs another person’s premises where an alternative route is available.
Source reference: para. 13; p. 5It further applied the principle that the distribution licensee may require compliance with necessary statutory and administrative formalities, including submission of premises-related documents, removal or shifting applications, and payment of charges raised in accordance with law.
Source reference: paras. 4, 10–12; pp. 2, 4Reasoning
The petitioner’s ownership of the premises was undisputed, and CESC had identified an alternative method of supplying electricity to the private respondents without using or disturbing the petitioner’s property.
Source reference: paras. 7–8; p. 3Accordingly, the Court held that CESC could not insist on continuing the existing arrangement merely because the private respondents had not separately requested removal of the meter and line.
Source reference: paras. 9–11; p. 4At the same time, the Court did not adjudicate the correctness of the Rs. 2,52,777/- bill; it left the financial and procedural aspects to be resolved between CESC and the private respondents in accordance with law.
Source reference: paras. 9–11; p. 4The private respondents were therefore required to complete all formalities and pay the requisite lawful charges within one month, failing which continued supply through the disputed arrangement could not be maintained.
Source reference: paras. 11–12; p. 4Holding
The writ petition was disposed of with a direction that CESC shift the electrical line and installations from the petitioner’s premises to premises occupied by the private respondents, subject to the private respondents’ compliance with all necessary formalities and payment of the requisite charges within one month from the date of the order.
If the private respondents failed to comply within that period, CESC was permitted to disconnect their electricity supply so that the petitioner would not continue to face disturbance.
Source reference: para. 12; p. 4The Court clarified that Section 43 of the Electricity Act, 2003 creates a duty to supply electricity but not a duty to supply it by disturbing another person when an alternative route exists.
Source reference: para. 13; p. 5The petition was disposed of without costs.
Source reference: para. 14; p. 5Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Electricity Act, 20031
Original Court PDF
ABHHOY CHARAN BASUvsCALCUTTA ELECTRIC SUPPLY CORPORATION LTD. AND ORS.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
