Facts
The applicant-contractor sought modification of the order dated 20 July 2026 passed in WPC No. 3744 of 2026, by which he had been granted a further and final opportunity to complete the remaining work under Tender No. 15-303, Pradhan Mantri Janman Yojna, Contract No. 336/PIU/2023–2024, within the stipulated period.
Source reference: para. 2, para. 5The applicant claimed that road-construction activities were required to remain closed from June until 15 October 2026 due to the rainy season, preventing completion of the work within the time granted by the Court.
Source reference: para. 3He submitted that only the asphalt/bitumen work remained and that the repair and maintenance work had already been completed. He sought extension of time until the end of December 2026 and stated that he was willing to complete the remaining work at his own risk.
Source reference: para. 3The State opposed the application, contending that Annexure P-3 was merely a WhatsApp conversation and not a formal order or notification issued by a competent authority.
Source reference: para. 4It further argued that the alleged rainy-season impediment had not been raised when the earlier order was passed.
Source reference: para. 4The applicant also alleged that payment for work already executed had not been sanctioned or released.
Source reference: para. 3Issues
1. Whether the order dated 20 July 2026 should be modified to extend the time for completion of the remaining contractual work until the end of December 2026 on the basis of subsequent events and the alleged rainy-season impediment?
Source reference: paras. 2–62. Whether the alleged impediment, supported by a document described as a WhatsApp conversation rather than a formal order or notification, could be adjudicated in the miscellaneous application seeking modification?
Source reference: paras. 4–63. Whether dismissal of the modification application would preclude the applicant from pursuing an independent legal remedy concerning any subsequent action or impediment affecting execution of the work?
Source reference: para. 7Law Applied
The Court applied the principle that a miscellaneous application for modification cannot be used to reopen or extend a period fixed by an earlier judicial order on the basis of subsequent events and disputed factual circumstances, particularly where the relevant ground was not placed before the Court when the original order was passed.
Source reference: paras. 5–6The Court further applied the principle that the legal nature and effect of an informal or disputed document—such as the WhatsApp communication relied upon by the applicant—could not appropriately be adjudicated in the present modification proceedings.
Source reference: para. 6The dismissal of a modification application does not bar an applicant from pursuing an independent remedy otherwise available in law in respect of a subsequent or separate grievance.
Source reference: para. 7Reasoning
The Court held that the rainy-season closure and alleged consequent impediment had not been brought to its notice when the order dated 20 July 2026 was passed.
Source reference: para. 5That order had already granted the applicant one further and final opportunity to complete the remaining work within the specified period.
Source reference: para. 5Accordingly, the applicant could not seek modification of that order by relying on a ground that was omitted from the earlier proceedings and on disputed subsequent facts.
Source reference: para. 5The Court also found that Annexure P-3 did not appear to be a formal order or notification of a competent authority; determining its authenticity, legal character, and effect would require adjudication beyond the scope of the miscellaneous application.
Source reference: para. 6The applicant’s assertions regarding completed work and pending payments likewise did not justify modification of the earlier time-bound direction.
Source reference: no citationHolding
The Court answered the principal issue against the applicant and held that no sufficient ground existed to modify or extend the period stipulated in the order dated 20 July 2026.
MCC No. 822 of 2026 was therefore dismissed, with no order as to costs.
Source reference: paras. 6, 8However, the dismissal did not preclude the applicant from pursuing any remedy otherwise available in law concerning a subsequent or independent grievance, including any later impediment allegedly caused by the respondents in completing the remaining work.
Source reference: para. 7Any such proceedings were to be considered by the competent forum on their own merits, without the High Court expressing an opinion on the merits or rights of the parties.
Source reference: para. 7Original Court PDF
M/s Netram SahuvsSTATE OF CHHATTISGARH
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
