Karnataka High Court
Arbitration and MediationContract Law

A price-adjustment claim fails when the contractor does not prove its contractual computation and quantum.

M/S. BSR INFRATECH INDIA LTD., vs STATE PROJECT DIRECTOR

Karnataka High CourtJUDGMENT: September 28, 20262 MIN READSOURCE JUDGMENT
A price-adjustment claim fails when the contractor does not prove its contractual computation and quantum.. M/S. BSR INFRATECH INDIA LTD., vs STATE PROJECT DIRECTOR. Karnataka High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

BSR sought payment for price adjustment under a construction contract with the State Project Director (SPD).

Source reference: para. 1, 24

The arbitral tribunal held that the price-adjustment clause formed part of the contract but rejected BSR’s claim of ₹4,53,24,186 because BSR had not established how the amount was calculated or produced supporting evidence.

Source reference: para. 24, 34–39

The Commercial Court dismissed BSR’s Section 34 petition. In the present appeal under Section 37 of the Arbitration and Conciliation Act, 1996, BSR challenged the rejection of its price-adjustment claim; its challenge was confined to that claim.

Source reference: para. 1, 24, 34–39
02

Issues

1. Whether the arbitral award’s rejection of BSR’s price-adjustment claim warranted interference under Section 34 of the Arbitration and Conciliation Act, 1996, where BSR had not substantiated the amount claimed.

Source reference: para. 24, 38–40

2. Whether the SPD’s alleged failure to dispute the quantum relieved BSR of the burden of establishing the amount claimed.

Source reference: para. 25, 32, 38–39
03

Law Applied

Section 34 of the Arbitration and Conciliation Act, 1996 provides the framework for challenging an arbitral award, while Section 37(1)(c) permits an appeal from an order refusing to set aside an award; the appeal was also brought under Section 13(1A) of the Commercial Courts Act, 2015.

Source reference: para. 1

Under Clause 40 of the contract, price adjustment was to be calculated using the applicable formulae in the Contract Data for specified cost components.

Source reference: para. 29–30

A party claiming payment must establish both its entitlement and the measure of the amount claimed; the judgment identifies no separate precedent as the basis for this principle.

Source reference: para. 32, 38–39
04

Reasoning

Although the tribunal accepted that the price-adjustment clause formed part of the contract, that finding did not establish the amount payable.

Source reference: para. 30–35

The Contract Data required calculation by specified formulae, but BSR provided no supporting calculation or evidence for the relevant variables. Its claim materials also stated inconsistent amounts, and the pleadings did not explain how the claimed sum had been computed.

Source reference: para. 30–35

The SPD’s denial of the claim meant BSR remained responsible for proving both entitlement and quantum; the court therefore found no basis to disturb the tribunal’s evidentiary conclusion.

Source reference: para. 36–39
05

Holding

The Court held that BSR had failed to establish the measure of its price-adjustment claim and found no ground to interfere with the arbitral award or the Commercial Court’s refusal to set it aside.

The appeal was dismissed.

Source reference: para. 39–41
06

Acts & Sections Cited

5 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Commercial Courts Act, 20151

Arbitration and Conciliation Act, 19964

Karnataka High Court

Original Court PDF

M/S. BSR INFRATECH INDIA LTD.,vsSTATE PROJECT DIRECTOR

Karnataka High Court · September 28, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment