Delhi High Court
Arbitration and MediationCivil Procedure and Evidence

A Section 36(3) stay application cannot compel the release of bank guarantees.

Consolidated Construction Consortium Ltd vs Oil And Natural Gas Corporation Ltd

Delhi High CourtJUDGMENT: September 29, 20262 MIN READSOURCE JUDGMENT
A Section 36(3) stay application cannot compel the release of bank guarantees.. Consolidated Construction Consortium Ltd vs Oil And Natural Gas Corporation Ltd. Delhi High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner challenged an arbitral award dated 29 November 2025 and obtained an interim stay of the findings against it, subject to keeping certain bank guarantees (BGs) alive.

Source reference: p. 2

It sought, under Section 36(3) of the Arbitration and Conciliation Act, 1996, release of BGs for liquidated damages, performance, and interest. In exchange, it offered to deposit ₹43,14,30,091 towards liquidated damages and ₹8,96,79,535 towards interest, and to permit set-off of ₹1,20,24,691 awarded to ONGC.

Source reference: pp. 2–4, 7–8

ONGC opposed the requested directions, arguing that Section 36(3) did not permit mandatory relief and noting that the petitioner had earlier sought similar relief under Section 9, without success.

Source reference: pp. 5–7

The Court had disposed of that Section 9 petition after recording ONGC’s undertaking not to act on its email if the BGs were extended.

Source reference: pp. 10–12
02

Issues

1. Whether the Court, while considering a stay application under Section 36(3) of the Act, could direct ONGC to release the BGs in return for the petitioner’s proposed deposits and set-off.

Source reference: pp. 8–10

2. Whether the petitioner’s earlier Section 9 proceedings affected its request for substantially similar relief under Section 36(3).

Source reference: pp. 5–6, 10–12
03

Law Applied

Section 36(2) provides that filing a Section 34 application does not by itself make an arbitral award unenforceable; a separate stay order is required. Under Section 36(3), the Court may stay the operation of an award, subject to conditions it considers fit and for reasons recorded in writing; the provision concerns a stay, not affirmative enforcement relief.

Source reference: pp. 8–9

Section 36(1) provides for enforcement of an award as a decree in accordance with the CPC, and the Court considered that relief akin to enforcement could be pursued through Section 36(1) and Order XXI of the CPC.

Source reference: p. 9

The Court also considered Home Care Retail Mart Pvt. Ltd. v. Haresh N. Sanghavi, which recognised an unsuccessful arbitration party’s ability to seek interim measures under Section 9, but held that it did not support ONGC’s contention on the scope of Section 36(3).

Source reference: p. 10
04

Reasoning

Although the petitioner’s proposed deposits and set-off appeared capable of securing ONGC’s interests, the Court held that equitable considerations could not expand Section 36(3) to authorise mandatory directions releasing the BGs.

Source reference: pp. 7–9, 12

The requested relief was akin to enforcement of the award and therefore was not properly sought through an application for stay under Section 36(3); treating it as available under that provision would undermine Section 36(1) and Order XXI of the CPC.

Source reference: pp. 9–10

The Court found that Home Care Retail Mart concerned access to Section 9 relief and did not resolve the issue before it.

Source reference: p. 10

It also noted the petitioner’s earlier Section 9 application for similar relief, which had been disposed of on the basis of the parties’ recorded statements regarding extension of the BGs.

Source reference: pp. 10–12
05

Holding

The Court declined to direct release of the liquidated-damages, performance, or interest BGs under Section 36(3), and disallowed prayers (b), (c), and (d).

It granted the petitioner one week to extend the BGs and left open the question whether renewal costs may be imposed on the opposing party if the renewing party ultimately succeeds.

Source reference: p. 12

The main petition was listed for 17 November 2026.

Source reference: p. 13
06

Acts & Sections Cited

3 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19963

Delhi High Court

Original Court PDF

Consolidated Construction Consortium LtdvsOil And Natural Gas Corporation Ltd

Delhi High Court · September 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment