Facts
The Appellant, a contractor, was awarded a tender for road and drain improvements in 2018
Source reference: p. 3Delays occurred in project execution, which the Appellant attributed to the Respondent’s failure to acquire private property, delay in providing drawings, and failure to relocate electrical poles
Source reference: p. 3-4The Appellant completed 72.2% of the work and submitted a price adjustment bill for ₹46,87,473 under Clause 40 of the General Conditions of Contract (GCC)
Source reference: p. 4When the Respondent failed to pay, the matter was referred to a Sole Arbitrator, who passed an award in favor of the Appellant on 14.03.2024
Source reference: p. 2, 5The Respondent, who stayed ex-parte during arbitration, challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996
Source reference: p. 8The Commercial Court set aside the award, finding an inherent contradiction between Clause 40 and 40.1 of the GCC and concluding that price adjustment should have been limited to "star rates" for specific materials as per a 2008 Government Order
Source reference: p. 9-10The Appellant then moved the High Court in appeal
Source reference: p. 2Issues
Whether the Commercial Court exceeded its jurisdiction under Section 34 of the A&C Act by re-adjudicating the merits of the price adjustment claim
Source reference: p. 11 / para. 18Whether an arbitral award can be set aside on the ground of "patent illegality" for an interpretative exercise of contract clauses that were not contested during arbitral proceedings
Source reference: p. 21 / para. 25-26Law Applied
The court primarily applied Section 34 of the Arbitration and Conciliation Act, 1996, which limits the grounds for setting aside an award to specific instances such as "patent illegality" appearing on the face of the award or conflict with the "public policy of India"
Source reference: p. 2, 21It relied on the principle that "patent illegality" must go to the root of the matter and cannot be invoked for mere errors in the interpretation of a contract
Source reference: p. 21The court also examined Clause 40 and 40.1 of the GCC alongside Government Orders dated 26.11.2004 and 21.11.2008 regarding price adjustments for labor, materials, and machinery
Source reference: p. 12, 19Reasoning
The High Court found that the Commercial Court had improperly embarked on a de novo adjudication of the price adjustment bill
Source reference: para. 17The Respondent had failed to participate in the arbitration or raise objections regarding the applicability of the 2008 Government Order at the relevant time
Source reference: para. 8, 28The High Court noted that Clause 40.1(a) allowed for price adjustments during extended periods of completion, and the Arbitral Tribunal had found the delays attributable to the Respondent
Source reference: para. 23The court reasoned that since the Appellant’s claim was sustainable under a plain reading of Clause 40.1 and its associated formulae (which included labor, fuel, and machinery), any perceived conflict between Clauses 40 and 40.1 was a matter of contractual interpretation
Source reference: para. 23-26Such interpretation falls within the sole domain of the Arbitrator and does not constitute "patent illegality" unless the view taken is perverse or impossible
Source reference: para. 26The court held that the Commercial Court erred by substituting its own interpretation for that of the Arbitrator on issues that were not even raised as grounds for challenge in the Section 34 petition
Source reference: para. 18, 25Holding
The High Court answered both issues in favor of the Appellant.
It held that the Commercial Court’s interference was unwarranted as the award was not vitiated by patent illegality or conflict with public policy
Source reference: para. 26, 29The High Court set aside the Commercial Court’s order dated 04.08.2025 and restored the arbitral award
Source reference: para. 30The appeal was allowed with no orders as to costs
Source reference: para. 30-31Original Court PDF
M/S S S Police Patil and Company v. The Deputy Commissioner, Dharwad District [COMAP No. 515 of 2025]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in