01Facts
The petitioners, residents of villages Pipliya Bhoju and Roshani affected by the Aullia Medium Irrigation Project, sought rehabilitation and resettlement benefits under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (“2013 Act”).
¶ 3–4They contended that the award dated 14 November 2018 did not include a separate Rehabilitation and Resettlement Award under Section 31.
¶ 3–4The State relied on a special package under a circular dated 27 July 2018 and undertakings by the petitioners accepting the package and its benefits. Those undertakings were filed with the State’s interlocutory application in 2025; the petitions, filed in 2021, had not disclosed them.
¶ 5–7The petitioners’ counsel stated that the petitioners were pressing the claims for a Section 31 award and acquisition of remaining lands in specified circumstances.
¶ 402Issues
i.1. Whether the petitioners could obtain a direction for a separate Rehabilitation and Resettlement Award under Section 31 after accepting benefits under the special package and furnishing undertakings.
¶ 4–5ii.2. Whether the petitions could be entertained when the petitioners had not disclosed their acceptance of the package and the undertakings in their pleadings.
¶ 6–703Law Applied
Section 31 of the 2013 Act was invoked by the petitioners as requiring a Rehabilitation and Resettlement Award.
¶ 3–4Sections 23 and 38 were also mentioned in the petitioners’ challenge to the acquisition and possession process.
¶ 3–4The petitioners relied on Ravir Singh & Ors. v. National Highway Authority of India & Competent Authority for Land Acquisition & Ors., but the Court did not apply or analyse that decision.
¶ 4Provisions in the judgment · 4 · Linked ones open on LawLens
Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 Section 23Section 31Section 38Section 41
04Reasoning
The Court found that the undertakings recorded acceptance of the special package and stated that the amount received would be treated as full and final settlement, while also providing for any further benefit that the Government might later grant.
¶ 6The acquisition award referred to the package and provided that any shortfall between the compensation and package amount would be paid as a special grant upon the required consent.
¶ 8In the Court’s view, the petitioners had accepted benefits under the package but had omitted that material fact from petitions filed in 2021; their subsequent claim for additional relief was therefore impermissible.
¶ 7–9The Court did not separately determine the general scope of Section 31.
¶ 905Holding
The Court rejected the petitioners’ claims.
¶ 9–10The Court dismissed both writ petitions, relying on their acceptance of the special package and their undisclosed undertakings.
¶ 9–10Original Court PDF
NannuvsUnion Of India
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
