Facts
The petitioners, residents of villages Pipliya Bhoju and Roshani affected by the Aullia Medium Irrigation Project, sought rehabilitation and resettlement benefits under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (“2013 Act”).
Source reference: para. 3–4They contended that the award dated 14 November 2018 did not include a separate Rehabilitation and Resettlement Award under Section 31.
Source reference: para. 3–4The State relied on a special package under a circular dated 27 July 2018 and undertakings by the petitioners accepting the package and its benefits. Those undertakings were filed with the State’s interlocutory application in 2025; the petitions, filed in 2021, had not disclosed them.
Source reference: para. 5–7The petitioners’ counsel stated that the petitioners were pressing the claims for a Section 31 award and acquisition of remaining lands in specified circumstances.
Source reference: para. 4Issues
1. Whether the petitioners could obtain a direction for a separate Rehabilitation and Resettlement Award under Section 31 after accepting benefits under the special package and furnishing undertakings.
Source reference: para. 4–52. Whether the petitions could be entertained when the petitioners had not disclosed their acceptance of the package and the undertakings in their pleadings.
Source reference: para. 6–7Law Applied
Section 31 of the 2013 Act was invoked by the petitioners as requiring a Rehabilitation and Resettlement Award.
Source reference: para. 3–4Sections 23 and 38 were also mentioned in the petitioners’ challenge to the acquisition and possession process.
Source reference: para. 3–4The petitioners relied on Ravir Singh & Ors. v. National Highway Authority of India & Competent Authority for Land Acquisition & Ors., but the Court did not apply or analyse that decision.
Source reference: para. 4Reasoning
The Court found that the undertakings recorded acceptance of the special package and stated that the amount received would be treated as full and final settlement, while also providing for any further benefit that the Government might later grant.
Source reference: para. 6The acquisition award referred to the package and provided that any shortfall between the compensation and package amount would be paid as a special grant upon the required consent.
Source reference: para. 8In the Court’s view, the petitioners had accepted benefits under the package but had omitted that material fact from petitions filed in 2021; their subsequent claim for additional relief was therefore impermissible.
Source reference: para. 7–9The Court did not separately determine the general scope of Section 31.
Source reference: para. 9Holding
The Court rejected the petitioners’ claims.
The Court dismissed both writ petitions, relying on their acceptance of the special package and their undisclosed undertakings.
Source reference: para. 9–10Acts & Sections Cited
4 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 20134
Original Court PDF
NannuvsUnion Of India
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
