Facts
The petitioner sought appointment of a sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996, in disputes arising from a Letter of Acceptance dated 8 January 2026 for construction work at Shivaji College, University of Delhi.
Source reference: p.1, para. 1RITES objected that the petitioner had not followed Clause 25 of the General Conditions of Contract, which required it first to seek a written decision from the Engineer-in-Chief and then, if necessary, appeal to the specified Appellate Authority.
Source reference: p.2, para. 2The petitioner had approached both authorities but received no response.
Source reference: p.2, para. 3RITES also contended that the dues had been settled in full and that there was accord and satisfaction.
Source reference: p.2, para. 4Issues
Whether the petitioner complied with Clause 25’s pre-arbitral procedure before invoking arbitration.
Source reference: p.2, para. 2Whether the alleged accord and satisfaction justified refusing a reference to arbitration at the Section 11(6) stage.
Source reference: p.2, para. 4Law Applied
Clause 25 of the contract required the contractor to seek a written decision from the Engineer-in-Chief and, if dissatisfied or if no decision was given within one month, to appeal to the designated Appellate Authority before invoking arbitration.
Source reference: p.2, para. 2Under Sections 11(6) and 11(6-A) of the Arbitration and Conciliation Act, 1996, the referral court’s inquiry is confined to a prima facie examination of the existence of the arbitration agreement; contested issues concerning discharge of the contract or accord and satisfaction are for the arbitral tribunal under Section 16.
Source reference: pp.9–11, paras. 10–11The Court relied principally on SBI General Insurance Co. Ltd. v. Krish Spinning, 2024 SCC OnLine SC 1754, which held that a dispute concerning full and final settlement does not extinguish the arbitration agreement and is ordinarily for the tribunal to decide.
Source reference: pp.4–7, paras. 6–7; pp.19–21, para. 11It also relied on Arabian Exports Pvt. Ltd. v. National Insurance Co. Ltd., (2025) 10 SCC 388, reaffirming that accord-and-satisfaction objections fall within the tribunal’s domain.
Source reference: pp.21–23, para. 12Reasoning
The Court rejected the procedural objection because the petitioner had first approached the Engineer-in-Chief and, after receiving no response, the competent Appellate Authority; it invoked arbitration only thereafter, as contemplated by Clause 25.
Source reference: p.2, para. 3As to accord and satisfaction, the objection concerned whether the petitioner’s claims had been settled, not whether an arbitration agreement existed.
Source reference: pp.19–23, paras. 11–13Applying Krish Spinning and Arabian Exports, the Court held that this mixed question of law and fact should be left to the arbitrator rather than determined in the Section 11 proceedings.
Source reference: pp.19–23, paras. 11–13Holding
The Court allowed the petition and appointed Mr. Bhagat Singh (Retd.), Special Director General, CPWD, as sole arbitrator, with fees to be fixed under the Fourth Schedule to the 1996 Act.
The arbitrator was directed to make the disclosure required by Section 12.
Source reference: p.24, para. 14The Court expressed no view on the merits, left all rights and contentions open, and permitted RITES to raise its accord-and-satisfaction objection before the arbitrator and to file a counterclaim, if any.
Source reference: p.24, paras. 15–17Acts & Sections Cited
8 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19967
Indian Contract Act, 18721
Original Court PDF
M/S Asian Construction CompanyvsRites Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in